| Assessment Year | 2025 |
|---|---|
| Principal Product | beer |
| NAICS | 312120: Breweries |
| SIC | 2082: Malt Beverages |
| Sales Range | less than $500 k |
| # of Employees | 6 |
| Plant Area |
20,070
ft2
|
| Annual Production | 4
Tgal
|
| Production Hrs. Annual | 2,794
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | ||
|---|---|---|---|---|---|
| Electricity Usage | $46,056 | 498,720 |
kWh
|
$0.092 | |
| Electricity Demand | $6,424 | 1,284 |
kW-mo/yr
|
$5.00 | |
| Electricity Fees | $4,607 | - |
|
- | |
| LPG | $48,625 | 1,519 |
MMBtu
|
$32.01 | |
| Other Energy | $3,063 | 1 |
MMBtu
|
$3,063.00 | |
| Waste Disposal Costs | |||||
| Water Usage | $3,914 | 1,793 |
Tgal
|
$2.18 | |
| TOTAL YEARLY COSTS | $112,689 | ||||
| RECOMMENDED SAVINGS* | $24,024 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
| IMPLEMENTED SAVINGS* | - | ||||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | By-product Production Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.9114: Use solar heat to make electricty | $17,614 | $149,397 |
$16,552
134,497
kWh
|
$1,062
-
kW-mo/yr
|
- | - | |
| 02 | 4.111: Add equipment/ operators to reduce production bottleneck | $3,901 | $142 | - | - | - | $3,901 | |
| 03 | 2.7226: Use computer programs to optimize hvac performance | $1,366 | $166 |
$1,146
12,421
kWh
|
$220
-
kW-mo/yr
|
- | - | |
| 04 | 2.7272: Install heat pipes / raise cooling setpoint | $420 | $72 |
$376
4,078
kWh
|
$44
-
kW-mo/yr
|
- | - | |
| 05 | 2.4231: Reduce the pressure of compressed air to the minimum required | $336 | $44 |
$283
3,062
kWh
|
$53
-
kW-mo/yr
|
- | - | |
| 06 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $255 | $197 |
$80
868
kWh
|
$8
-
kW-mo/yr
|
$167 | - | |
| 07 | 2.7132: Install timers on light switches in little used areas | $132 | $254 |
$132
1,417
kWh
|
- | - | - | |
| TOTAL RECOMMENDED | $24,024 | $150,272 |
$18,569
156,343
kWh
|
$1,387
-
kW-mo/yr
|
$167 | $3,901 | ||
| TOTAL IMPLEMENTED | - | - | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | By-product Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs