ITAC Assessment: AS0595
ITAC logo
ITAC Assessment: AS0595
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2025
Principal Product beer
NAICS 312120: Breweries
SIC 2082: Malt Beverages
Sales Range less than $500
k
# of Employees 6
Plant Area 20,070
ft2
Annual Production 4
Tgal
Production Hrs. Annual 2,794
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $46,056 498,720
kWh
Electricity Demand $6,424 1,284
kW-mo/yr
Electricity Fees $4,607 -
LPG $48,625 1,519
MMBtu
Other Energy $3,063 1
MMBtu
Waste Disposal Costs
Water Usage $3,914 1,793
Tgal
TOTAL YEARLY COSTS $112,689
RECOMMENDED SAVINGS* $24,024 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings By-product Production Savings
01 2.9114: Use solar heat to make electricty $17,614 $149,397 $16,552
134,497
kWh
$1,062
-
kW-mo/yr
- -
02 4.111: Add equipment/ operators to reduce production bottleneck $3,901 $142 - - - $3,901
03 2.7226: Use computer programs to optimize hvac performance $1,366 $166 $1,146
12,421
kWh
$220
-
kW-mo/yr
- -
04 2.7272: Install heat pipes / raise cooling setpoint $420 $72 $376
4,078
kWh
$44
-
kW-mo/yr
- -
05 2.4231: Reduce the pressure of compressed air to the minimum required $336 $44 $283
3,062
kWh
$53
-
kW-mo/yr
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $255 $197 $80
868
kWh
$8
-
kW-mo/yr
$167 -
07 2.7132: Install timers on light switches in little used areas $132 $254 $132
1,417
kWh
- - -
TOTAL RECOMMENDED $24,024 $150,272 $18,569
156,343
kWh
$1,387
-
kW-mo/yr
$167 $3,901
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs