ITAC Assessment: AS0587
ITAC logo
ITAC Assessment: AS0587
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Education
NAICS 611110: Elementary and Secondary Schools
SIC 8211: Elementary and Secondary Schools
Sales Range less than $500
k
# of Employees 120
Plant Area 1,001,856
ft2
Annual Production 1
units
Production Hrs. Annual 2,550
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $177,622 1,235,661
kWh
Electricity Demand $30,640 3,833
kW-mo/yr
Electricity Fees $26,970 -
Natural Gas $20,345 2,810
MMBtu
Waste Disposal Costs
Water Usage $28,707 8,867
Tgal
TOTAL YEARLY COSTS $284,284
RECOMMENDED SAVINGS* $111,504 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Ancillary Material Cost Savings
01 2.8112: Combine utility meters $30,741 $605 $28,692
-
kWh
$(-3,189.0)
-
kW-mo/yr
$5,238 -
02 2.9114: Use solar heat to make electricty $23,057 $176,288 $20,787
185,595
kWh
$2,270
-
kW-mo/yr
- -
03 2.9114: Use solar heat to make electricty $17,501 $95,089 $17,055
93,866
kWh
$446
-
kW-mo/yr
- -
04 2.7132: Install timers on light switches in little used areas $13,232 $5,780 $13,232
94,194
kWh
- - -
05 2.9114: Use solar heat to make electricty $10,418 $95,089 $9,738
92,833
kWh
$680
-
kW-mo/yr
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $7,127 $21,892 $6,181
34,029
kWh
$791
-
kW-mo/yr
- $155
07 2.7144: Install spectral reflectors / delamp $4,422 - $1,909
13,655
kWh
$638
-
kW-mo/yr
- $1,875
08 2.7272: Install heat pipes / raise cooling setpoint $3,680 $136 $3,345
18,408
kWh
$335
-
kW-mo/yr
- -
09 2.7135: Install occupancy sensors $1,326 $2,077 $1,132
6,438
kWh
$194
-
kW-mo/yr
- -
TOTAL RECOMMENDED $111,504 $396,956 $102,071
539,018
kWh
$2,165
-
kW-mo/yr
$5,238 $2,030
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs