ITAC Assessment: AS0576
ITAC logo
ITAC Assessment: AS0576
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Reclaimed water
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range less than $500
k
# of Employees 25
Plant Area 3,390,468
ft2
Annual Production 16,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,431,896 16,649,948
kWh
Electricity Demand $164,041 32,483
kW-mo/yr
Electricity Fees $137,227 -
TOTAL YEARLY COSTS $1,733,164
RECOMMENDED SAVINGS* $237,020 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
01 2.9114: Use solar heat to make electricty $188,394 $1,306,404 $169,850
1,975,005
kWh
$18,544
-
kW-mo/yr
-
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $39,891 $18,800 $36,028
418,925
kWh
$3,863
-
kW-mo/yr
-
03 4.611: Begin a practice of predictive / preventative maintenance $3,250 $1,245 $3,250
37,791
kWh
- -
04 2.7224: Reduce space conditioning during non-working hours $3,027 $160 $2,178
26,325
kWh
$849
-
kW-mo/yr
-
05 2.7132: Install timers on light switches in little used areas $886 $700 $886
10,303
kWh
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $872 $1,035 $545
6,342
kWh
$53
-
kW-mo/yr
$274
07 2.7226: Use computer programs to optimize hvac performance $562 $2,900 $562
6,533
kWh
- -
08 2.7272: Install heat pipes / raise cooling setpoint $138 $90 $130
1,522
kWh
$8
-
kW-mo/yr
-
TOTAL RECOMMENDED $237,020 $1,331,334 $213,429
2,482,746
kWh
$23,317
-
kW-mo/yr
$274
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs