ITAC Assessment: AS0566
ITAC logo
ITAC Assessment: AS0566
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2024
Principal Product Dietary Supplements
NAICS 325411: Medicinal and Botanical Manufacturing
SIC 2833: Medicinal Chemicals and Botanical Products
Sales Range $10
M
to 50
M
# of Employees 100
Plant Area 55,000
ft2
Annual Production 800,000,000
units
Production Hrs. Annual 4,286
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $80,152 865,200
kWh
Electricity Demand $16,029 3,206
kW-mo/yr
Electricity Fees $4,110 -
Waste Disposal Costs
Water Usage $2,609 1,083
Tgal
TOTAL YEARLY COSTS $102,900
RECOMMENDED SAVINGS* $33,443 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $33,263

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.9114: Use solar heat to make electricty $29,582 $284,735 $29,387
317,350
kWh
$195
-
kW-mo/yr
02 2.7135: Install occupancy sensors $1,673 $3,459 $1,458
15,732
kWh
$215
-
kW-mo/yr
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,411 $463 $1,234
13,322
kWh
$177
-
kW-mo/yr
04 2.4322: Use or replace with energy efficient substitutes $404 $496 $379
4,088
kWh
$25
-
kW-mo/yr
05 2.7423: Reduce heat gain by window tinting $193 $667 $179
1,928
kWh
$14
-
kW-mo/yr
06 2.4231: Reduce the pressure of compressed air to the minimum required $180 $44 $160
1,732
kWh
$20
-
kW-mo/yr
TOTAL RECOMMENDED $33,443 $289,864 $32,797
354,152
kWh
$646
-
kW-mo/yr
TOTAL IMPLEMENTED $33,263 $289,820 $32,637
352,420
kWh
$626
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs