Assessment Year | 2023 |
---|---|
Principal Product | Truck water systems, tanks and tank kits |
NAICS | 332420: Metal Tank (Heavy Gauge) Manufacturing |
SIC | 3713: Truck and Bus Bodies |
Sales Range | $10 M to 50M |
# of Employees | 29 |
Plant Area |
60,147
ft2
|
Annual Production | 189
units
|
Production Hrs. Annual | 2,600
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | ||
---|---|---|---|---|---|
Electricity Usage | $69,012 | 586,000 |
kWh
|
$0.12 | |
Electricity Demand | $31,864 | 2,872 |
kW-mo/yr
|
$11.09 | |
Electricity Fees | $5,401 | - |
|
- | |
Natural Gas | $11,415 | 741 |
MMBtu
|
$15.40 | |
Waste Disposal Costs | |||||
Water Usage | $18,319 | 2,288 |
Tgal
|
$8.01 | |
TOTAL YEARLY COSTS | $136,011 | ||||
RECOMMENDED SAVINGS* | $41,122 |
See individual recommendations below
*Non-energy impacts included in savings.
|
|||
IMPLEMENTED SAVINGS* | $9,326 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.9114: Use solar heat to make electricty | $30,388 | $182,064 |
$27,958
237,334
kWh
|
$2,430
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,294 | $1,654 |
$3,558
30,200
kWh
|
$456
-
kW-mo/yr
|
- | $280 | |
03 | 2.7226: Use computer programs to optimize hvac performance | $2,752 | $63 |
$2,416
20,510
kWh
|
$336
-
kW-mo/yr
|
- | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $2,251 | $143 |
$1,991
16,900
kWh
|
$260
-
kW-mo/yr
|
- | - | |
05 | 2.7135: Install occupancy sensors | $945 | $110 |
$814
6,914
kWh
|
$131
-
kW-mo/yr
|
- | - | |
06 | 2.7272: Install heat pipes / raise cooling setpoint | $463 | $71 |
$459
3,893
kWh
|
$4
-
kW-mo/yr
|
- | - | |
07 | 3.4154: Eliminate leaks in water lines and valves | $29 | $79 | - | - |
$29
-
Tgal
|
- | |
TOTAL RECOMMENDED | $41,122 | $184,184 |
$37,196
315,751
kWh
|
$3,617
-
kW-mo/yr
|
$29
-
Tgal
|
$280 | ||
TOTAL IMPLEMENTED | $9,326 | $1,939 |
$7,965
67,610
kWh
|
$1,052
-
kW-mo/yr
|
$29
-
Tgal
|
$280 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Usage Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs