| Assessment Year | 2023 |
|---|---|
| Principal Product | Hospitality services |
| NAICS | 721110: Hotels (except Casino Hotels) and Motels |
| SIC | 7011: Hotels and Motels |
| Sales Range | $10 M to 50M |
| # of Employees | 300 |
| Plant Area |
625,289
ft2
|
| Annual Production | 1
units
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $176,451 | 3,929,176 |
kWh
|
$0.045 |
| Electricity Demand | $123,079 | 7,534 |
kW-mo/yr
|
$16.34 |
| Electricity Fees | $94,082 | - |
|
- |
| Natural Gas | $241,262 | 62,995 |
MMBtu
|
$3.83 |
| TOTAL YEARLY COSTS | $634,874 | |||
| RECOMMENDED SAVINGS* | $62,976 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $38,441 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7272: Install heat pipes / raise cooling setpoint | $24,380 | $2,114 |
$12,276
273,394
kWh
|
$12,104
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7226: Use computer programs to optimize hvac performance | $20,707 | $53,376 |
$6,175
137,521
kWh
|
$6,087
-
kW-mo/yr
|
$8,445
-
MMBtu
|
- | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $9,261 | $14,447 |
$5,250
116,978
kWh
|
$2,683
-
kW-mo/yr
|
- | $1,328 | - | |
| 04 | 2.1133: Adjust burners for efficient operation | $4,800 | $481 | - | - |
$4,930
-
MMBtu
|
- | $(-130.0) | |
| 05 | 2.7135: Install occupancy sensors | $3,177 | $4,584 |
$2,118
47,238
kWh
|
$1,059
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.7144: Install spectral reflectors / delamp | $651 | $106 |
$404
9,004
kWh
|
$201
-
kW-mo/yr
|
- | $46 | - | |
| TOTAL RECOMMENDED | $62,976 | $75,108 |
$26,223
584,135
kWh
|
$22,134
-
kW-mo/yr
|
$13,375
-
MMBtu
|
$1,374 | $(-130.0) | ||
| TOTAL IMPLEMENTED | $38,441 | $17,042 |
$17,526
390,372
kWh
|
$14,787
-
kW-mo/yr
|
$4,930
-
MMBtu
|
$1,328 | $(-130.0) | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs