| Assessment Year | 2023 |
|---|---|
| Principal Product | metal powders |
| NAICS | 332117: Powder Metallurgy Part Manufacturing |
| SIC | 3499: Fabricated Metal Products, Not Elsewhere Classified |
| Sales Range | $50 M to 100M |
| # of Employees | 95 |
| Plant Area |
52,000
ft2
|
| Annual Production | 2,866,009
lb
|
| Production Hrs. Annual | 5,000
hrs
|
| Location (State) | New Mexico |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $240,497 | 4,339,200 |
kWh
|
$0.055 |
| Electricity Demand | $316,013 | 17,466 |
kW-mo/yr
|
$18.09 |
| Electricity Fees | $37,776 | - |
|
- |
| Other Energy | $970,928 | 179,830 |
MMBtu
|
$5.40 |
| TOTAL YEARLY COSTS | $1,565,214 | |||
| RECOMMENDED SAVINGS* | $781,424 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $80,147 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings | Primary Product Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 3.1191: Change procedures / equipment / operating conditions | $701,165 | $7,692,249 | - | - | $(-269,763.0) | - | $970,928 | |
| 02 | 2.9114: Use solar heat to make electricty | $51,728 | $659,540 |
$35,610
642,771
kWh
|
$16,118
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4321: Upgrade obsolete equipment | $21,635 | $819,000 |
$21,635
390,528
kWh
|
- | - | - | - | |
| 04 | 2.4322: Use or replace with energy efficient substitutes | $5,025 | $75,360 | - | - | - | $5,025 | - | |
| 05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,759 | $9,900 |
$1,008
18,198
kWh
|
$751
-
kW-mo/yr
|
- | - | - | |
| 06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $112 | $414 |
$58
1,053
kWh
|
$54
-
kW-mo/yr
|
- | - | - | |
| TOTAL RECOMMENDED | $781,424 | $9,256,463 |
$58,311
1,052,550
kWh
|
$16,923
-
kW-mo/yr
|
$(-269,763.0) | $5,025 | $970,928 | ||
| TOTAL IMPLEMENTED | $80,147 | $1,563,800 |
$58,253
1,051,497
kWh
|
$16,869
-
kW-mo/yr
|
- | $5,025 | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Ancillary Material Cost Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs