ITAC Assessment: AS0551
ITAC logo
ITAC Assessment: AS0551
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product Hospitality services
NAICS 721110: Hotels (except Casino Hotels) and Motels
SIC 7011: Hotels and Motels
Sales Range $500
k
to 1
M
# of Employees 5
Plant Area 11,870
ft2
Annual Production 1
units
Production Hrs. Annual 4,745
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $7,959 113,695
kWh
Electricity Demand $3,497 426
kW-mo/yr
Electricity Fees $8,232 -
Natural Gas $3,878 378
MMBtu
Waste Disposal Costs
Water Usage $12,289 717
Tgal
TOTAL YEARLY COSTS $35,855
RECOMMENDED SAVINGS* $6,601 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $6,601

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Water Usage Savings Ancillary Material Cost Savings
01 3.4156: Use flow control valves on equipment to optimize water use $2,434 $2,202 - - $677
-
MMBtu
$1,757
-
Tgal
-
02 2.4322: Use or replace with energy efficient substitutes $1,528 $7,174 $1,316
18,802
kWh
$212
-
kW-mo/yr
- - -
03 4.611: Begin a practice of predictive / preventative maintenance $1,477 $3,284 $1,477
21,100
kWh
- - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $784 $3,277 $244
3,488
kWh
$245
-
kW-mo/yr
- - $295
05 2.7134: Use photocell controls $378 $819 $307
4,380
kWh
$71
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $6,601 $16,756 $3,344
47,770
kWh
$528
-
kW-mo/yr
$677
-
MMBtu
$1,757
-
Tgal
$295
TOTAL IMPLEMENTED $6,601 $16,756 $3,344
47,770
kWh
$528
-
kW-mo/yr
$677
-
MMBtu
$1,757
-
Tgal
$295
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs