ITAC Assessment: AS0538
ITAC logo
ITAC Assessment: AS0538
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2023
Principal Product 200mm silicon wafers
NAICS 334413: Semiconductor and Related Device Manufacturing
SIC 3674: Semiconductors and Related Devices
Sales Range $100
M
to 500
M
# of Employees 390
Plant Area 1,500,000
ft2
Annual Production 2,940,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $2,319,821 74,452,000
kWh
Electricity Demand $1,752,987 220,310
kW-mo/yr
Electricity Fees $1,398,044 -
Natural Gas $437,752 58,686
MMBtu
Waste Disposal Costs
Water Usage $1,549,471 292,778
Tgal
TOTAL YEARLY COSTS $7,458,075
RECOMMENDED SAVINGS* $1,288,923 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
01 2.9114: Use solar heat to make electricty $722,230 $2,223,000 $579,237
18,565,298
kWh
$142,993
-
kW-mo/yr
- -
02 2.1223: Install smaller boiler (increase high fire duty cycle) $290,625 $126,000 - - $290,625
-
MMBtu
-
03 2.7226: Use computer programs to optimize hvac performance $170,279 $17,076 $81,302
2,605,820
kWh
$88,977
-
kW-mo/yr
- -
04 2.7232: Replace existing hvac unit with high efficiency model $99,703 $442,407 $47,605
1,525,803
kWh
$52,098
-
kW-mo/yr
- -
05 2.7134: Use photocell controls $3,648 $8,619 $2,733
87,600
kWh
$915
-
kW-mo/yr
- -
06 2.7142: Utilize higher efficiency lamps and/or ballasts $2,438 $3,603 $1,627
52,114
kWh
$454
-
kW-mo/yr
- $357
TOTAL RECOMMENDED $1,288,923 $2,820,705 $712,504
22,836,635
kWh
$285,437
-
kW-mo/yr
$290,625
-
MMBtu
$357
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs