ITAC Assessment: AS0533
ITAC logo
ITAC Assessment: AS0533
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2022
Principal Product engraving machines
NAICS 423710: Hardware Merchant Wholesalers
SIC 5072: Hardware
Sales Range $100
M
to 500
M
# of Employees 150
Plant Area 137,000
ft2
Annual Production 5,400
units
Production Hrs. Annual 2,184
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $148,666 2,245,458
kWh
Electricity Demand $55,731 6,746
kW-mo/yr
Electricity Fees $10,775 -
Waste Disposal Costs
Water Usage $21,892 4,479
Tgal
TOTAL YEARLY COSTS $237,064
RECOMMENDED SAVINGS* $86,036 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $27,362

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
01 2.9114: Use solar heat to make electricty $57,834 $453,050 $49,161
742,612
kWh
$8,673
-
kW-mo/yr
-
02 2.7142: Utilize higher efficiency lamps and/or ballasts $15,662 $30,425 $11,171
168,749
kWh
$3,705
-
kW-mo/yr
$786
03 2.7272: Install heat pipes / raise cooling setpoint $11,409 $630 $6,841
103,334
kWh
$4,568
-
kW-mo/yr
-
04 2.7444: Close holes and openings in building such as broken windows $597 $163 $407
6,150
kWh
$190
-
kW-mo/yr
-
05 2.7132: Install timers on light switches in little used areas $291 $600 $291
4,391
kWh
- -
06 2.7496: Install partitions to reduce size of conditioned space $243 $852 $165
2,499
kWh
$78
-
kW-mo/yr
-
TOTAL RECOMMENDED $86,036 $485,720 $68,036
1,027,735
kWh
$17,214
-
kW-mo/yr
$786
TOTAL IMPLEMENTED $27,362 $31,655 $18,303
276,474
kWh
$8,273
-
kW-mo/yr
$786
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs