ITAC Assessment: AS0508
ITAC logo
ITAC Assessment: AS0508
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Potable Water
NAICS 221310: Water Supply and Irrigation Systems
SIC 4941: Water Supply
Sales Range less than $500
k
# of Employees 75
Plant Area 118,718
ft2
Annual Production 1,250,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $255,604 2,890,792
kWh
Electricity Demand $48,498 6,040
kW-mo/yr
Electricity Fees $384 -
TOTAL YEARLY COSTS $304,486
RECOMMENDED SAVINGS* $102,161 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,589

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
01 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $79,572 $28,606 $70,731
803,759
kWh
$8,841
-
kW-mo/yr
-
02 3.1161: Eliminate/reduce an operation $20,000 $200 - - $20,000
03 2.7241: Install outside air damper / economizer on hvac unit $1,773 $1,500 $1,468
16,679
kWh
$305
-
kW-mo/yr
-
04 2.7272: Install heat pipes / raise cooling setpoint $427 $114 $330
3,754
kWh
$97
-
kW-mo/yr
-
05 2.7142: Utilize higher efficiency lamps and/or ballasts $389 $529 $339
3,849
kWh
$40
-
kW-mo/yr
$10
TOTAL RECOMMENDED $102,161 $30,949 $72,868
828,041
kWh
$9,283
-
kW-mo/yr
$20,010
TOTAL IMPLEMENTED $22,589 $2,343 $2,137
24,282
kWh
$442
-
kW-mo/yr
$20,010
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs