ITAC Assessment: AS0506
ITAC logo
ITAC Assessment: AS0506
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Dehydrated Fruits
NAICS 311423: Dried and Dehydrated Food Manufacturing
SIC 2034: Dried and Dehydrated Fruits, Vegetables, and Soup Mixes
Sales Range less than $500
k
# of Employees 8
Plant Area 125,000
ft2
Annual Production 25,000,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $297,615 5,492,160
kWh
Electricity Demand $351,953 21,427
kW-mo/yr
Electricity Fees $7,203 -
TOTAL YEARLY COSTS $656,771
RECOMMENDED SAVINGS* $160,549 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings One-time Revenue or Avoided Cost Savings
01 2.8112: Combine utility meters $83,765 $2,853 $45,123
-
kWh
$34,957
-
kW-mo/yr
$3,685 -
02 2.4323: Use optimum size and capacity equipment $32,780 $1,503 $20,469
377,676
kWh
$12,311
-
kW-mo/yr
- -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $16,228 $16,466 $11,275
208,018
kWh
$5,172
-
kW-mo/yr
- $(-219.0)
04 4.114: Add/modify equipment to improve drying process $11,446 $21,173 $7,888
145,542
kWh
$3,558
-
kW-mo/yr
- -
05 2.7232: Replace existing hvac unit with high efficiency model $8,417 $27,733 $4,043
74,591
kWh
$4,374
-
kW-mo/yr
- -
06 2.7135: Install occupancy sensors $7,913 $1,399 $7,913
146,001
kWh
- - -
TOTAL RECOMMENDED $160,549 $71,127 $96,711
951,828
kWh
$60,372
-
kW-mo/yr
$3,685 $(-219.0)
TOTAL IMPLEMENTED - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs