Assessment Year | 2021 |
---|---|
Principal Product | Treated Wastewater |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | less than $500 k |
# of Employees | 9 |
Plant Area |
20,000
ft2
|
Annual Production | 985,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $162,349 | 4,257,600 |
kWh
|
$0.038 |
Electricity Demand | $156,535 | 8,360 |
kW-mo/yr
|
$18.72 |
Electricity Fees | $39,811 | - |
|
- |
TOTAL YEARLY COSTS | $358,695 | |||
RECOMMENDED SAVINGS* | $88,625 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $4,085 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $42,454 | $940 |
$26,280
691,572
kWh
|
$16,174
-
kW-mo/yr
|
- | |
02 | 2.4131: Size electric motors for peak operating efficiency | $36,391 | $37,849 |
$16,341
430,016
kWh
|
$11,550
-
kW-mo/yr
|
$8,500 | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,005 | $7,546 |
$1,839
48,408
kWh
|
$1,312
-
kW-mo/yr
|
$(-146.0) | |
04 | 2.7232: Replace existing hvac unit with high efficiency model | $2,172 | $7,423 |
$879
23,148
kWh
|
$1,293
-
kW-mo/yr
|
- | |
05 | 2.7272: Install heat pipes / raise cooling setpoint | $1,787 | $103 |
$724
19,047
kWh
|
$1,063
-
kW-mo/yr
|
- | |
06 | 2.4111: Utilize energy-efficient belts and other improved mechanisms | $1,736 | $1,408 |
$1,373
36,131
kWh
|
$363
-
kW-mo/yr
|
- | |
07 | 2.7135: Install occupancy sensors | $1,080 | $2,877 |
$1,080
28,409
kWh
|
- | - | |
TOTAL RECOMMENDED | $88,625 | $58,146 |
$48,516
1,276,731
kWh
|
$31,755
-
kW-mo/yr
|
$8,354 | ||
TOTAL IMPLEMENTED | $4,085 | $10,423 |
$2,919
76,817
kWh
|
$1,312
-
kW-mo/yr
|
$(-146.0) | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs