ITAC Assessment: AS0496
ITAC logo
ITAC Assessment: AS0496
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Treated Wastewater
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range less than $500
k
# of Employees 6
Plant Area 4,260
ft2
Annual Production 511,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $132,646 2,133,000
kWh
Electricity Demand $57,099 5,076
kW-mo/yr
Electricity Fees $18,753 -
TOTAL YEARLY COSTS $208,498
RECOMMENDED SAVINGS* $198,987 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $24,229

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings By-product Production Savings
01 3.5313: Increase amount of waste recovered for resale $174,284 $89,232 - - $(-221,558.0) $80,482 $315,360
02 2.4323: Use optimum size and capacity equipment $18,309 $3,941 $15,193
253,222
kWh
$3,116
-
kW-mo/yr
- - -
03 2.6218: Turn off equipment when not in use $2,587 $789 $2,059
34,316
kWh
$528
-
kW-mo/yr
- - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $1,402 $3,920 $1,290
18,329
kWh
$328
-
kW-mo/yr
- $(-216.0) -
05 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $1,262 $6,259 $756
12,614
kWh
$506
-
kW-mo/yr
- - -
06 2.7272: Install heat pipes / raise cooling setpoint $499 $35 $324
5,406
kWh
$175
-
kW-mo/yr
- - -
07 2.6231: Utilize controls to operate equipment only when needed $474 $188 $377
6,276
kWh
$97
-
kW-mo/yr
- - -
08 2.7135: Install occupancy sensors $170 $275 $170
2,836
kWh
- - - -
TOTAL RECOMMENDED $198,987 $104,639 $20,169
332,999
kWh
$4,750
-
kW-mo/yr
$(-221,558.0) $80,266 $315,360
TOTAL IMPLEMENTED $24,229 $15,219 $19,792
326,723
kWh
$4,653
-
kW-mo/yr
- $(-216.0) -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs