Assessment Year | 2021 |
---|---|
Principal Product | Treated Wastewater |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | less than $500 k |
# of Employees | 6 |
Plant Area |
4,260
ft2
|
Annual Production | 511,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $132,646 | 2,133,000 |
kWh
|
$0.062 |
Electricity Demand | $57,099 | 5,076 |
kW-mo/yr
|
$11.25 |
Electricity Fees | $18,753 | - |
|
- |
TOTAL YEARLY COSTS | $208,498 | |||
RECOMMENDED SAVINGS* | $198,987 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $24,229 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 3.5313: Increase amount of waste recovered for resale | $174,284 | $89,232 | - | - | $(-221,558.0) | $80,482 | $315,360 | |
02 | 2.4323: Use optimum size and capacity equipment | $18,309 | $3,941 |
$15,193
253,222
kWh
|
$3,116
-
kW-mo/yr
|
- | - | - | |
03 | 2.6218: Turn off equipment when not in use | $2,587 | $789 |
$2,059
34,316
kWh
|
$528
-
kW-mo/yr
|
- | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,402 | $3,920 |
$1,290
18,329
kWh
|
$328
-
kW-mo/yr
|
- | $(-216.0) | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $1,262 | $6,259 |
$756
12,614
kWh
|
$506
-
kW-mo/yr
|
- | - | - | |
06 | 2.7272: Install heat pipes / raise cooling setpoint | $499 | $35 |
$324
5,406
kWh
|
$175
-
kW-mo/yr
|
- | - | - | |
07 | 2.6231: Utilize controls to operate equipment only when needed | $474 | $188 |
$377
6,276
kWh
|
$97
-
kW-mo/yr
|
- | - | - | |
08 | 2.7135: Install occupancy sensors | $170 | $275 |
$170
2,836
kWh
|
- | - | - | - | |
TOTAL RECOMMENDED | $198,987 | $104,639 |
$20,169
332,999
kWh
|
$4,750
-
kW-mo/yr
|
$(-221,558.0) | $80,266 | $315,360 | ||
TOTAL IMPLEMENTED | $24,229 | $15,219 |
$19,792
326,723
kWh
|
$4,653
-
kW-mo/yr
|
- | $(-216.0) | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Ancillary Material Cost Savings | One-time Revenue or Avoided Cost Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs