Assessment Year | 2021 |
---|---|
Principal Product | Treated Wastewater |
NAICS | 221320: Sewage Treatment Facilities |
SIC | 4952: Sewerage Systems |
Sales Range | less than $500 k |
# of Employees | 7 |
Plant Area |
7,700
ft2
|
Annual Production | 273,000
Tgal
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $69,547 | 1,013,760 |
kWh
|
$0.069 |
Electricity Demand | $20,471 | 1,929 |
kW-mo/yr
|
$10.61 |
Electricity Fees | $8,543 | - |
|
- |
TOTAL YEARLY COSTS | $98,561 | |||
RECOMMENDED SAVINGS* | $40,531 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $26,134 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | One-time Revenue or Avoided Cost Savings |
---|---|---|---|---|---|---|---|
01 | 2.4323: Use optimum size and capacity equipment | $23,643 | $3,941 |
$20,280
289,720
kWh
|
$3,363
-
kW-mo/yr
|
- | |
02 | 2.9114: Use solar heat to make electricty | $14,397 | $249,210 |
$13,666
226,980
kWh
|
$731
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,621 | $908 |
$1,253
17,897
kWh
|
$263
-
kW-mo/yr
|
$105 | |
04 | 2.7135: Install occupancy sensors | $732 | $612 |
$732
10,464
kWh
|
- | - | |
05 | 2.7272: Install heat pipes / raise cooling setpoint | $138 | $33 |
$95
1,356
kWh
|
$43
-
kW-mo/yr
|
- | |
TOTAL RECOMMENDED | $40,531 | $254,704 |
$36,026
546,417
kWh
|
$4,400
-
kW-mo/yr
|
$105 | ||
TOTAL IMPLEMENTED | $26,134 | $5,494 |
$22,360
319,437
kWh
|
$3,669
-
kW-mo/yr
|
$105 |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs