ITAC Assessment: AS0492
ITAC logo
ITAC Assessment: AS0492
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2021
Principal Product Treated Wastewater
NAICS 221320: Sewage Treatment Facilities
SIC 4952: Sewerage Systems
Sales Range less than $500
k
# of Employees 10
Plant Area 3,816
ft2
Annual Production 91,000
Tgal
Production Hrs. Annual 8,760
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $48,428 514,200
kWh
Electricity Demand $24,320 2,609
kW-mo/yr
Electricity Fees $4,097 -
TOTAL YEARLY COSTS $76,845
RECOMMENDED SAVINGS* $29,684 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $22,378

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
01 2.4323: Use optimum size and capacity equipment $16,087 $3,941 $13,114
145,708
kWh
$2,973
-
kW-mo/yr
-
02 2.6218: Turn off equipment when not in use $6,291 $789 $5,516
61,290
kWh
$775
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $3,170 $4,695 $2,625
29,131
kWh
$375
-
kW-mo/yr
$170
04 2.4314: Use synthetic lubricant $1,708 $300 $1,271
14,128
kWh
$289
-
kW-mo/yr
$148
05 3.6192: Use a less expensive method of waste removal $1,465 $244 - - $1,465
06 2.6125: Keep equipment clean $743 $464 $743
8,258
kWh
- -
07 2.7135: Install occupancy sensors $220 $612 $220
2,376
kWh
- -
TOTAL RECOMMENDED $29,684 $11,045 $23,489
260,891
kWh
$4,412
-
kW-mo/yr
$1,783
TOTAL IMPLEMENTED $22,378 $4,730 $18,630
206,998
kWh
$3,748
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs