| Assessment Year | 2020 |
|---|---|
| Principal Product | Treated Wastewater |
| NAICS | 221320: Sewage Treatment Facilities |
| SIC | 4952: Sewerage Systems |
| Sales Range | less than $500 k |
| # of Employees | 11 |
| Plant Area |
30,000
ft2
|
| Annual Production | 2,000,000
Tgal
|
| Production Hrs. Annual | 8,760
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $632,133 | 9,156,662 |
kWh
|
$0.069 |
| Electricity Demand | $83,560 | 15,989 |
kW-mo/yr
|
$5.23 |
| Electricity Fees | $61,539 | - |
|
- |
| TOTAL YEARLY COSTS | $777,232 | |||
| RECOMMENDED SAVINGS* | $266,363 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $180,477 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.4323: Use optimum size and capacity equipment | $176,974 | $3,941 |
$163,403
2,368,160
kWh
|
$13,571
-
kW-mo/yr
|
- | - | |
| 02 | 2.8112: Combine utility meters | $69,299 | $735 |
$107,959
-
kWh
|
$(-30,500.0)
-
kW-mo/yr
|
$(-8,160.0) | - | |
| 03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $16,587 | $9,520 |
$15,066
218,353
kWh
|
$1,521
-
kW-mo/yr
|
- | - | |
| 04 | 2.7135: Install occupancy sensors | $1,757 | $511 |
$1,757
25,458
kWh
|
- | - | - | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,511 | $2,230 |
$1,323
19,167
kWh
|
$136
-
kW-mo/yr
|
- | $52 | |
| 06 | 2.7272: Install heat pipes / raise cooling setpoint | $235 | $38 |
$180
2,606
kWh
|
$55
-
kW-mo/yr
|
- | - | |
| TOTAL RECOMMENDED | $266,363 | $16,975 |
$289,688
2,633,744
kWh
|
$(-15,217.0)
-
kW-mo/yr
|
$(-8,160.0) | $52 | ||
| TOTAL IMPLEMENTED | $180,477 | $6,720 |
$166,663
2,415,391
kWh
|
$13,762
-
kW-mo/yr
|
- | $52 | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | One-time Revenue or Avoided Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs