ITAC Assessment: AS0488
ITAC logo
ITAC Assessment: AS0488
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2020
Principal Product Asphalt Paving Material
NAICS 324121: Asphalt Paving Mixture and Block Manufacturing
SIC 2951: Asphalt Paving Mixtures and Blocks
Sales Range less than $500
k
# of Employees 32
Plant Area 100,000
ft2
Annual Production 1,300,000
ton
Production Hrs. Annual 3,570
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $525,278 6,378,020
kWh
Electricity Demand $157,633 34,300
kW-mo/yr
Electricity Fees $9,926 -
TOTAL YEARLY COSTS $692,837
RECOMMENDED SAVINGS* $169,586 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $125,419

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
01 2.8114: Change rate schedules or other changes in utility service $118,609 $10,790 $111,716
-
kWh
$10,869
-
kW-mo/yr
$(-3,976.0) -
02 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $41,944 $27,312 $34,270
428,370
kWh
$7,674
-
kW-mo/yr
- -
03 3.4154: Eliminate leaks in water lines and valves $2,602 $272 $2,125
26,558
kWh
$477
-
kW-mo/yr
- -
04 2.7272: Install heat pipes / raise cooling setpoint $2,344 $36 $2,299
28,748
kWh
$45
-
kW-mo/yr
- -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $1,864 $7,653 $1,892
23,655
kWh
$113
-
kW-mo/yr
- $(-141.0)
06 2.4111: Utilize energy-efficient belts and other improved mechanisms $1,828 $3,940 $1,368
17,104
kWh
$460
-
kW-mo/yr
- -
07 2.7135: Install occupancy sensors $395 $1,840 $395
4,935
kWh
- - -
TOTAL RECOMMENDED $169,586 $51,843 $154,065
529,370
kWh
$19,638
-
kW-mo/yr
$(-3,976.0) $(-141.0)
TOTAL IMPLEMENTED $125,419 $18,751 $118,032
78,961
kWh
$11,504
-
kW-mo/yr
$(-3,976.0) $(-141.0)
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs