| Assessment Year | 2019 |
|---|---|
| Principal Product | Cement/Ready Mix |
| NAICS | 327320: Ready-Mix Concrete Manufacturing |
| SIC | 3273: Ready-Mixed Concrete |
| Sales Range | $10 M to 50M |
| # of Employees | 15 |
| Plant Area |
2,000
ft2
|
| Annual Production | 6,000
units
|
| Production Hrs. Annual | 3,333
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $26,989 | 341,200 |
kWh
|
$0.079 |
| Electricity Demand | $71,194 | 4,388 |
kW-mo/yr
|
$16.22 |
| Electricity Fees | $7,659 | - |
|
- |
| TOTAL YEARLY COSTS | $105,842 | |||
| RECOMMENDED SAVINGS* | $65,851 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $28,283 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.3131: Reschedule plant operations or reduce load to avoid peaks | $25,716 | $2,242 | - | - | $25,716 | |
| 02 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $16,212 | $45,350 |
$12,627
126,265
kWh
|
$3,585
-
kW-mo/yr
|
- | |
| 03 | 2.6218: Turn off equipment when not in use | $13,813 | $447 |
$12,379
123,785
kWh
|
$1,434
-
kW-mo/yr
|
- | |
| 04 | 2.4133: Use most efficient type of electric motors | $7,543 | $27,245 |
$6,417
64,167
kWh
|
$1,126
-
kW-mo/yr
|
- | |
| 05 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,567 | $2,918 |
$2,000
19,998
kWh
|
$567
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $65,851 | $78,202 |
$33,423
334,215
kWh
|
$6,712
-
kW-mo/yr
|
$25,716 | ||
| TOTAL IMPLEMENTED | $28,283 | $5,160 |
$2,000
19,998
kWh
|
$567
-
kW-mo/yr
|
$25,716 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs