Assessment Year | 2018 |
---|---|
Principal Product | Packaged Ice |
NAICS | 312113: Ice Manufacturing |
SIC | 2097: Manufactured Ice |
Sales Range | $50 M to 100M |
# of Employees | 60 |
Plant Area |
80,000
ft2
|
Annual Production | 200,000,000
lb
|
Production Hrs. Annual | 7,300
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,128,432 | 12,912,476 |
kWh
|
$0.087 |
Electricity Demand | $193,237 | 32,193 |
kW-mo/yr
|
$6.00 |
TOTAL YEARLY COSTS | $1,321,669 | |||
RECOMMENDED SAVINGS* | $381,478 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4133: Use most efficient type of electric motors | $274,952 | $196,499 |
$246,461
2,823,154
kWh
|
$28,491
-
kW-mo/yr
|
|
02 | 2.6222: Use drying oven (batch type) on alternate days or other optimum schedule to run equipment with full loads | $64,677 | - |
$64,677
740,880
kWh
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $13,697 | $12,185 |
$12,185
139,577
kWh
|
$1,512
-
kW-mo/yr
|
|
04 | 3.1162: Use less wasteful packaging | $12,596 | $196 |
$12,596
144,279
kWh
|
- | |
05 | 2.3113: Make ice during off peak hours for cooling | $11,530 | $150 |
$2,553
29,249
kWh
|
$8,977
-
kW-mo/yr
|
|
06 | 2.2511: Insulate bare equipment | $4,026 | $3,043 |
$3,616
41,423
kWh
|
$410
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $381,478 | $212,073 |
$342,088
3,918,562
kWh
|
$39,390
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs