Assessment Year | 2006 |
---|---|
Principal Product | Milk |
NAICS | 311511: Fluid Milk Manufacturing |
SIC | 2026: Fluid Milk |
Sales Range | $50 M to 100M |
# of Employees | 40 |
Plant Area |
2,306,794
ft2
|
Annual Production | 31,000
Tgal
|
Production Hrs. Annual | 4,318
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $187,869 | 3,636,640 |
kWh
|
$0.052 |
Natural Gas | $106,883 | 12,090 |
MMBtu
|
$8.84 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $18,997 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $16,327 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Demand Savings | Natural Gas Savings |
---|---|---|---|---|---|---|
01 | 2.2135: Repair and eliminate steam leaks | $11,573 | $500 | - |
$11,573
-
MMBtu
|
|
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,372 | $15,000 |
$4,372
-
kW-mo/yr
|
- | |
03 | 2.1233: Analyze flue gas for proper air/fuel ratio | $2,670 | $1,000 | - |
$2,670
-
MMBtu
|
|
04 | 2.2136: Install / repair insulation on steam lines | $382 | $99 | - |
$382
-
MMBtu
|
|
TOTAL RECOMMENDED | $18,997 | $16,599 |
$4,372
-
kW-mo/yr
|
$14,625
-
MMBtu
|
||
TOTAL IMPLEMENTED | $16,327 | $15,599 |
$4,372
-
kW-mo/yr
|
$11,955
-
MMBtu
|
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs