ITAC Assessment: AS0424
ITAC logo
ITAC Assessment: AS0424
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Treated lumber
NAICS 321114: Wood Preservation
SIC 2491: Wood Preserving
Sales Range $10
M
to 50
M
# of Employees 46
Plant Area 1,306,794
ft2
Annual Production 48,000,000
units
Production Hrs. Annual 6,096
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $77,051 809,360
kWh
Electricity Demand $16,426 10,842
kW-mo/yr
Natural Gas $128,808 12,554
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,930 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.2135: Repair and eliminate steam leaks $6,478 $800 - - $6,478
-
MMBtu
02 2.4133: Use most efficient type of electric motors $4,125 $44,393 $3,774
50,392
kWh
$351
-
kW-mo/yr
-
03 2.1233: Analyze flue gas for proper air/fuel ratio $3,418 $1,000 - - $3,418
-
MMBtu
04 2.2136: Install / repair insulation on steam lines $2,909 $2,240 - - $2,909
-
MMBtu
TOTAL RECOMMENDED $16,930 $48,433 $3,774
50,392
kWh
$351
-
kW-mo/yr
$12,805
-
MMBtu
TOTAL IMPLEMENTED - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs