ITAC Assessment: AS0419
ITAC logo
ITAC Assessment: AS0419
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2006
Principal Product Melamine products
NAICS 326199: All Other Plastics Product Manufacturing
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 135
Plant Area 37,000
ft2
Annual Production 19,540
pieces
Production Hrs. Annual 6,048
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $48,760 649,508
kWh
Electricity Demand $7,718 1,585
kW-mo/yr
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $5,273 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.4231: Reduce the pressure of compressed air to the minimum required $2,620 $1,000 $2,351
28,710
kWh
$269
-
kW-mo/yr
02 2.4231: Reduce the pressure of compressed air to the minimum required $1,482 $7,500 $1,330
16,235
kWh
$152
-
kW-mo/yr
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,171 $5,000 $1,051
12,835
kWh
$120
-
kW-mo/yr
TOTAL RECOMMENDED $5,273 $13,500 $4,732
57,780
kWh
$541
-
kW-mo/yr
TOTAL IMPLEMENTED - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs