ITAC Assessment: AS0400
ITAC logo
ITAC Assessment: AS0400
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2005
Principal Product Circuit Boards for Gaming Machinery
NAICS 334418: Printed Circuit Assembly (Electronic Assembly) Manufacturing
SIC 3629: Electrical Industrial Apparatus, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 160
Plant Area 128,000
ft2
Annual Production 30,000,000
pieces
Production Hrs. Annual 2,168
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $52,219 803,653
kWh
Electricity Demand $3,148 3,364
kW-mo/yr
Electricity Fees $25,764 -
Natural Gas $7,995 1,047
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $163,281 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Primary Product Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $289 $500 $280
4,392
kWh
$9
-
kW-mo/yr
-
02 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,262 $5,000 $1,222
18,909
kWh
$40
-
kW-mo/yr
-
03 2.7135: Install occupancy sensors $224 $750 $224
3,450
kWh
- -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $2,555 $18,393 $2,412
37,156
kWh
$143
-
kW-mo/yr
-
05 2.6212: Turn off equipment during breaks, reduce operating time $8,951 $100 $8,951
137,757
kWh
- -
06 4.112: Replace old machine with new automatic multi-station tool $150,000 $80,000 - - $150,000
TOTAL RECOMMENDED $163,281 $104,743 $13,089
201,664
kWh
$192
-
kW-mo/yr
$150,000
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs