| Assessment Year | 2004 |
|---|---|
| Principal Product | Aircraft Tire Retreading |
| NAICS | 326212: Tire Retreading |
| SIC | 7534: Tire Retreading and Repair Shops |
| Sales Range | $5 M to 10M |
| # of Employees | 49 |
| Plant Area |
54,000
ft2
|
| Annual Production | 48,000
pieces
|
| Production Hrs. Annual | 6,240
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $167,695 | 3,146,240 |
kWh
|
$0.053 |
| Electricity Demand | $70,184 | 7,388 |
kW-mo/yr
|
$9.50 |
| Electricity Fees | $57,973 | - |
|
- |
| Natural Gas | $95,961 | 12,495 |
MMBtu
|
$7.68 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $58,873 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $50,081 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings |
|---|---|---|---|---|---|---|---|
| 01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $50,081 | $440 |
$39,873
526,029
kWh
|
$10,208
-
kW-mo/yr
|
- | |
| 02 | 2.2511: Insulate bare equipment | $1,489 | $815 | - | - |
$1,489
-
MMBtu
|
|
| 03 | 2.1392: Replace purchased steam with other energy source | $366 | $1,530 |
$366
4,828
kWh
|
- | - | |
| 04 | 2.2414: Use waste heat from hot flue gases to preheat | $283 | $800 | - | - |
$283
-
MMBtu
|
|
| 05 | 2.4133: Use most efficient type of electric motors | $1,196 | $1,247 |
$953
12,564
kWh
|
$243
-
kW-mo/yr
|
- | |
| 06 | 2.7232: Replace existing hvac unit with high efficiency model | $953 | $1,400 |
$631
8,320
kWh
|
$322
-
kW-mo/yr
|
- | |
| 07 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $4,505 | $1,477 |
$3,588
47,334
kWh
|
$917
-
kW-mo/yr
|
- | |
| TOTAL RECOMMENDED | $58,873 | $7,709 |
$45,411
599,075
kWh
|
$11,690
-
kW-mo/yr
|
$1,772
-
MMBtu
|
||
| TOTAL IMPLEMENTED | $50,081 | $440 |
$39,873
526,029
kWh
|
$10,208
-
kW-mo/yr
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs