ITAC Assessment: AS0375
ITAC logo
ITAC Assessment: AS0375
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Aircraft Parts and Auxiliary Equipment
NAICS 336413: Other Aircraft Parts and Auxiliary Equipment Manufacturing
SIC 3728: Aircraft Parts and Auxiliary Equipment, Not Elsewhere Classified
Sales Range $10
M
to 50
M
# of Employees 90
Plant Area 34,100
ft2
Annual Production 40,000
pieces
Production Hrs. Annual 4,042
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $95,123 1,152,319
kWh
Electricity Demand $7,821 4,831
kW-mo/yr
Electricity Fees $6,581 -
Natural Gas $19,385 2,378
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $16,917 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $1,768

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $6,472 $11,485 $2,319
32,036
kWh
$4,153
-
kW-mo/yr
02 2.7135: Install occupancy sensors $880 $900 $880
12,150
kWh
-
03 2.7232: Replace existing hvac unit with high efficiency model $7,797 $26,415 $6,847
94,583
kWh
$950
-
kW-mo/yr
04 2.4231: Reduce the pressure of compressed air to the minimum required $468 $737 $468
6,466
kWh
-
05 2.4231: Reduce the pressure of compressed air to the minimum required $168 $60 $139
1,923
kWh
$29
-
kW-mo/yr
06 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,132 $30 $937
12,943
kWh
$195
-
kW-mo/yr
TOTAL RECOMMENDED $16,917 $39,627 $11,590
160,101
kWh
$5,327
-
kW-mo/yr
TOTAL IMPLEMENTED $1,768 $827 $1,544
21,332
kWh
$224
-
kW-mo/yr
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs