Assessment Year | 2004 |
---|---|
Principal Product | Printed Circuit Boards |
NAICS | 334412: Bare Printed Circuit Board Manufacturing |
SIC | 3672: Printed Circuit Boards |
Sales Range | $50 M to 100M |
# of Employees | 720 |
Plant Area |
275,000
ft2
|
Annual Production | 208,000
pieces
|
Production Hrs. Annual | 7,488
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $1,149,844 | 18,970,166 |
kWh
|
$0.061 |
Electricity Fees | $9,223 | - |
|
- |
Natural Gas | $9,223 | 952 |
MMBtu
|
$9.69 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $64,594 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings |
---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $20,289 | $150 |
$12,448
365,071
kWh
|
$7,841
-
kW-mo/yr
|
|
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $14,258 | $39,378 |
$9,490
229,481
kWh
|
$4,768
-
kW-mo/yr
|
|
03 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $15,336 | $12,650 |
$9,413
276,035
kWh
|
$5,923
-
kW-mo/yr
|
|
04 | 2.7232: Replace existing hvac unit with high efficiency model | $10,545 | $16,000 |
$4,614
118,562
kWh
|
$5,931
-
kW-mo/yr
|
|
05 | 2.4133: Use most efficient type of electric motors | $2,794 | $1,844 |
$2,327
45,194
kWh
|
$467
-
kW-mo/yr
|
|
06 | 2.4323: Use optimum size and capacity equipment | $1,372 | $5,500 |
$1,203
21,715
kWh
|
$169
-
kW-mo/yr
|
|
TOTAL RECOMMENDED | $64,594 | $75,522 |
$39,495
1,056,058
kWh
|
$25,099
-
kW-mo/yr
|
||
TOTAL IMPLEMENTED | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs