ITAC Assessment: AS0369
ITAC logo
ITAC Assessment: AS0369
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2004
Principal Product Dairy
NAICS 112120: Dairy Cattle and Milk Production
SIC 241: Logging
Sales Range $1
M
to 5
M
# of Employees 20
Plant Area 1,000,000
ft2
Annual Production 29,200,000
lb
Production Hrs. Annual 8,760
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $25,551 2,947
kWh
Electricity Demand $7,799 2,947
kW-mo/yr
Electricity Fees $4,700 -
LPG $47,300 430
MMBtu
Fuel Oil #2 $47,300 3,660
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $38,890 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $904

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
01 2.3414: Burn waste to produce steam to drive a steam turbine generator set and use steam exhaust for heat $33,626 $16,440 $21,924
548,100
kWh
$7,102
-
kW-mo/yr
$4,600
-
MMBtu
02 2.2622: Replace existing chiller with high efficiency model $1,848 $10,300 $1,434
37,741
kWh
$414
-
kW-mo/yr
-
03 2.9112: Use solar heat to heat water $1,305 $1,740 - - $1,305
-
MMBtu
04 2.4231: Reduce the pressure of compressed air to the minimum required $988 - $636
16,740
kWh
$352
-
kW-mo/yr
-
05 2.7232: Replace existing hvac unit with high efficiency model $749 $3,500 $390
10,267
kWh
$359
-
kW-mo/yr
-
06 2.4133: Use most efficient type of electric motors $219 $79 $155
4,069
kWh
$64
-
kW-mo/yr
-
07 2.2511: Insulate bare equipment $155 $240 $155
4,079
kWh
- -
TOTAL RECOMMENDED $38,890 $32,299 $24,694
620,996
kWh
$8,291
-
kW-mo/yr
$5,905
-
MMBtu
TOTAL IMPLEMENTED $904 $3,740 $545
14,346
kWh
$359
-
kW-mo/yr
-
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs