Assessment Year | 2003 |
---|---|
Principal Product | Milk |
NAICS | 112120: Dairy Cattle and Milk Production |
SIC | 241: Logging |
Sales Range | $1 M to 5M |
# of Employees | 10 |
Plant Area |
1,400,000
ft2
|
Annual Production | 19,400,000
lb
|
Production Hrs. Annual | 5,840
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $57,413 | 850,781 |
kWh
|
$0.067 |
Electricity Demand | $14,196 | 1,917 |
kW-mo/yr
|
$7.41 |
Electricity Fees | $3,065 | - |
|
- |
Natural Gas | $573 | 46 |
MMBtu
|
$12.46 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $91,379 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $5,768 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Increase in Production Savings |
---|---|---|---|---|---|---|---|---|---|
01 | 4.451: Add additional production shift | $66,315 | $18,116 | - | - | - | - | $66,315 | |
02 | 4.111: Add equipment/ operators to reduce production bottleneck | $11,700 | $18,000 | - | - | - | - | $11,700 | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,140 | $60 |
$3,837
7,464
kWh
|
$303
-
kW-mo/yr
|
- | - | - | |
04 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $6,660 | $7,180 |
$3,349
65,159
kWh
|
$3,311
-
kW-mo/yr
|
- | - | - | |
05 | 4.631: Install an uninteruptable power supply | $1,275 | $573 | - | - | - | $1,275 | - | |
06 | 2.9112: Use solar heat to heat water | $468 | $1,730 | - | - |
$468
-
MMBtu
|
- | - | |
07 | 2.2222: Convert liquid heaters from underfiring to immersion or submersion heating | $468 | $1,150 | - | - |
$468
-
MMBtu
|
- | - | |
08 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $353 | $1,640 |
$246
6,482
kWh
|
$107
-
kW-mo/yr
|
- | - | - | |
TOTAL RECOMMENDED | $91,379 | $48,449 |
$7,432
79,105
kWh
|
$3,721
-
kW-mo/yr
|
$936
-
MMBtu
|
$1,275 | $78,015 | ||
TOTAL IMPLEMENTED | $5,768 | $2,273 |
$4,083
13,946
kWh
|
$410
-
kW-mo/yr
|
- | $1,275 | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Administrative Changes Savings | Increase in Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs