ITAC Assessment: AS0366
ITAC logo
ITAC Assessment: AS0366
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2003
Principal Product Milk
NAICS 112120: Dairy Cattle and Milk Production
SIC 241: Logging
Sales Range $1
M
to 5
M
# of Employees 10
Plant Area 1,400,000
ft2
Annual Production 19,400,000
lb
Production Hrs. Annual 5,840
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $57,413 850,781
kWh
Electricity Demand $14,196 1,917
kW-mo/yr
Electricity Fees $3,065 -
Natural Gas $573 46
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $91,379 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $5,768

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Increase in Production Savings
01 4.451: Add additional production shift $66,315 $18,116 - - - - $66,315
02 4.111: Add equipment/ operators to reduce production bottleneck $11,700 $18,000 - - - - $11,700
03 2.4231: Reduce the pressure of compressed air to the minimum required $4,140 $60 $3,837
7,464
kWh
$303
-
kW-mo/yr
- - -
04 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $6,660 $7,180 $3,349
65,159
kWh
$3,311
-
kW-mo/yr
- - -
05 4.631: Install an uninteruptable power supply $1,275 $573 - - - $1,275 -
06 2.9112: Use solar heat to heat water $468 $1,730 - - $468
-
MMBtu
- -
07 2.2222: Convert liquid heaters from underfiring to immersion or submersion heating $468 $1,150 - - $468
-
MMBtu
- -
08 2.7142: Utilize higher efficiency lamps and/or ballasts $353 $1,640 $246
6,482
kWh
$107
-
kW-mo/yr
- - -
TOTAL RECOMMENDED $91,379 $48,449 $7,432
79,105
kWh
$3,721
-
kW-mo/yr
$936
-
MMBtu
$1,275 $78,015
TOTAL IMPLEMENTED $5,768 $2,273 $4,083
13,946
kWh
$410
-
kW-mo/yr
- $1,275 -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Natural Gas Savings Administrative Changes Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs