| Assessment Year | 2003 |
|---|---|
| Principal Product | Concrete Pipe and Steel Pipe |
| NAICS | 327332: Concrete Pipe Manufacturing |
| SIC | 3272: Concrete Products, Except Block and Brick |
| Sales Range | $10 M to 50M |
| # of Employees | 100 |
| Plant Area |
1,916,640
ft2
|
| Annual Production | 0
units
|
| Production Hrs. Annual | 3,125
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $255,874 | 4,032,599 |
kWh
|
$0.063 |
| Electricity Demand | $21,307 | 12,887 |
kW-mo/yr
|
$1.65 |
| Electricity Fees | $16,380 | - |
|
- |
| Natural Gas | $89,206 | 9,643 |
MMBtu
|
$9.25 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $48,046 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $45,171 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings |
|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $892 | $4,873 |
$530
11,669
kWh
|
$212
-
kW-mo/yr
|
- | $150 | |
| 02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $42,103 | $570 |
$28,318
622,911
kWh
|
$13,785
-
kW-mo/yr
|
- | - | |
| 03 | 2.4314: Use synthetic lubricant | $1,388 | $2,160 |
$918
20,198
kWh
|
$470
-
kW-mo/yr
|
- | - | |
| 04 | 2.7232: Replace existing hvac unit with high efficiency model | $295 | $1,000 |
$289
6,367
kWh
|
$6
-
kW-mo/yr
|
- | - | |
| 05 | 2.4133: Use most efficient type of electric motors | $279 | $1,990 |
$187
6,879
kWh
|
$92
-
kW-mo/yr
|
- | - | |
| 06 | 2.4239: Eliminate or reduce compressed air usage | $1,983 | $300 |
$1,924
42,328
kWh
|
$59
-
kW-mo/yr
|
- | - | |
| 07 | 2.2136: Install / repair insulation on steam lines | $1,106 | $1,264 | - | - |
$1,106
-
MMBtu
|
- | |
| TOTAL RECOMMENDED | $48,046 | $12,157 |
$32,166
710,352
kWh
|
$14,624
-
kW-mo/yr
|
$1,106
-
MMBtu
|
$150 | ||
| TOTAL IMPLEMENTED | $45,171 | $6,984 |
$29,712
656,355
kWh
|
$14,353
-
kW-mo/yr
|
$1,106
-
MMBtu
|
- | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Ancillary Material Cost Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs