Assessment Year | 2003 |
---|---|
Principal Product | Aerospace and Computer Products |
NAICS | 332710: Machine Shops |
SIC | 3599: Industrial and Commercial Machinery and Equipment, Not Elsewhere Classified |
Sales Range | $10 M to 50M |
# of Employees | 75 |
Plant Area |
28,000
ft2
|
Annual Production | 3,600
units
|
Production Hrs. Annual | 7,296
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $96,830 | 1,339,080 |
kWh
|
$0.072 |
Electricity Demand | $40,221 | 2,877 |
kW-mo/yr
|
$13.98 |
Electricity Fees | $13,712 | - |
|
- |
Natural Gas | $2,943 | 264 |
MMBtu
|
$11.15 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $15,160 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $6,293 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|
01 | 2.4231: Reduce the pressure of compressed air to the minimum required | $1,888 | $30 |
$1,610
23,645
kWh
|
$278
-
kW-mo/yr
|
- | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $4,284 | $30 |
$3,654
53,657
kWh
|
$630
-
kW-mo/yr
|
- | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,718 | $9,268 |
$3,106
45,605
kWh
|
$612
-
kW-mo/yr
|
- | |
04 | 2.7145: Install skylights | $2,387 | $5,219 |
$2,387
35,057
kWh
|
- | - | |
05 | 2.7232: Replace existing hvac unit with high efficiency model | $1,550 | $2,600 | n/a |
$1,323
14,919
kWh
|
$227
-
kW-mo/yr
|
- |
06 | 2.7221: Lower temperature during the winter season and vice-versa | $121 | - |
$68
1,004
kWh
|
$53
-
kW-mo/yr
|
- | |
07 | 3.5242: Recover metals from spent solutions and recycle | $1,212 | $44 | - | - | $1,212 | |
TOTAL RECOMMENDED | $15,160 | $17,191 |
$12,148
173,887
kWh
|
$1,800
-
kW-mo/yr
|
$1,212 | ||
TOTAL IMPLEMENTED | $6,293 | $60 |
$5,332
78,306
kWh
|
$961
-
kW-mo/yr
|
- | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs