ITAC Assessment: AS0340
ITAC logo
ITAC Assessment: AS0340
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Private label facial and bathroom tissue, napkins, towels, etc.
NAICS
n/a
SIC 2676: Sanitary Paper Products
Sales Range $50
M
to 100
M
# of Employees 131
Plant Area 450,000
ft2
Annual Production 5,000,000
units
Production Hrs. Annual 8,760
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $885,627 10,774,569
kWh
Natural Gas $35,213 4,289
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $261,797 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $87,552

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,113 $5,518 $972
12,858
kWh
$141
-
kW-mo/yr
- - - -
02 2.7135: Install occupancy sensors $340 $600 $340
4,495
kWh
- - - - -
03 2.7145: Install skylights $36,748 $54,898 $36,748
486,092
kWh
- - - - -
04 2.4133: Use most efficient type of electric motors $2,190 - $2,093
30,920
kWh
$97
-
kW-mo/yr
- - - -
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $155 $20 $148
1,955
kWh
$7
-
kW-mo/yr
- - - -
06 2.4231: Reduce the pressure of compressed air to the minimum required $4,051 $30 $3,830
56,580
kWh
$221
-
kW-mo/yr
- - - -
07 2.4314: Use synthetic lubricant $13,263 $6,971 $8,901
117,734
kWh
$460
-
kW-mo/yr
- $3,902
-
gal
- -
08 2.3212: Optimize plant power factor $6,618 $1,590 - - $6,618 - - -
09 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $73,135 $13,732 $69,514
1,027,190
kWh
$3,621
-
kW-mo/yr
- - - -
10 3.5315: Lease / purchase baler; sell cardboard to recycler $5,400 $8,554 - - - - $5,400
-
lb
-
11 4.611: Begin a practice of predictive / preventative maintenance $25,624 $4,800 - - - - - $25,624
12 4.111: Add equipment/ operators to reduce production bottleneck $32,500 $6,000 - - - - - $32,500
13 4.521: Clear and rent existing space $60,660 $8,804 - - - - - $60,660
TOTAL RECOMMENDED $261,797 $111,517 $122,546
1,737,824
kWh
$4,547
-
kW-mo/yr
$6,618 $3,902
-
gal
$5,400
-
lb
$118,784
TOTAL IMPLEMENTED $87,552 $19,142 $1,120
14,813
kWh
$148
-
kW-mo/yr
- - - $86,284
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Electricity Fees Savings Other Liquid (non-haz) Savings Solid Waste (non-haz) Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs