Assessment Year | 2002 |
---|---|
Principal Product | Private label facial and bathroom tissue, napkins, towels, etc. |
NAICS |
n/a
|
SIC | 2676: Sanitary Paper Products |
Sales Range | $50 M to 100M |
# of Employees | 131 |
Plant Area |
450,000
ft2
|
Annual Production | 5,000,000
units
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Nevada |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $885,627 | 10,774,569 |
kWh
|
$0.082 |
Natural Gas | $35,213 | 4,289 |
MMBtu
|
$8.21 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $261,797 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $87,552 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,113 | $5,518 |
$972
12,858
kWh
|
$141
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7135: Install occupancy sensors | $340 | $600 |
$340
4,495
kWh
|
- | - | - | - | - | |
03 | 2.7145: Install skylights | $36,748 | $54,898 |
$36,748
486,092
kWh
|
- | - | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $2,190 | - |
$2,093
30,920
kWh
|
$97
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $155 | $20 |
$148
1,955
kWh
|
$7
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $4,051 | $30 |
$3,830
56,580
kWh
|
$221
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.4314: Use synthetic lubricant | $13,263 | $6,971 |
$8,901
117,734
kWh
|
$460
-
kW-mo/yr
|
- |
$3,902
-
gal
|
- | - | |
08 | 2.3212: Optimize plant power factor | $6,618 | $1,590 | - | - | $6,618 | - | - | - | |
09 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $73,135 | $13,732 |
$69,514
1,027,190
kWh
|
$3,621
-
kW-mo/yr
|
- | - | - | - | |
10 | 3.5315: Lease / purchase baler; sell cardboard to recycler | $5,400 | $8,554 | - | - | - | - |
$5,400
-
lb
|
- | |
11 | 4.611: Begin a practice of predictive / preventative maintenance | $25,624 | $4,800 | - | - | - | - | - | $25,624 | |
12 | 4.111: Add equipment/ operators to reduce production bottleneck | $32,500 | $6,000 | - | - | - | - | - | $32,500 | |
13 | 4.521: Clear and rent existing space | $60,660 | $8,804 | - | - | - | - | - | $60,660 | |
TOTAL RECOMMENDED | $261,797 | $111,517 |
$122,546
1,737,824
kWh
|
$4,547
-
kW-mo/yr
|
$6,618 |
$3,902
-
gal
|
$5,400
-
lb
|
$118,784 | ||
TOTAL IMPLEMENTED | $87,552 | $19,142 |
$1,120
14,813
kWh
|
$148
-
kW-mo/yr
|
- | - | - | $86,284 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Electricity Fees Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs