ITAC Assessment: AS0323
ITAC logo
ITAC Assessment: AS0323
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2002
Principal Product Kitchen and bathroom wood cabinets
NAICS
n/a
SIC 2434: Wood Kitchen Cabinets
Sales Range $10
M
to 50
M
# of Employees 260
Plant Area 135,000
ft2
Annual Production 1,000,000
pieces
Production Hrs. Annual 6,006
hrs
Location (State) Nevada

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $105,227 1,682,070
kWh
Electricity Demand $20,171 4,394
kW-mo/yr
Electricity Fees $15,349 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $175,254 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $164,605

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
01 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $23,932 $220 $20,202
285,746
kWh
$3,730
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $3,163 $3,020 $2,757
38,632
kWh
$406
-
kW-mo/yr
- - -
03 2.7135: Install occupancy sensors $276 $375 $227
3,183
kWh
$49
-
kW-mo/yr
- - -
04 2.7121: Utilize daylight whenever possible in lieu of artificial light $6,114 $540 $6,114
86,486
kWh
- - - -
05 2.7221: Lower temperature during the winter season and vice-versa $633 - $481
6,734
kWh
$152
-
kW-mo/yr
- - -
06 2.7232: Replace existing hvac unit with high efficiency model $1,096 $2,100 $955
13,371
kWh
$141
-
kW-mo/yr
- - -
07 3.5248: Separate and recycle scrap metal to foundry or for sale $1,800 $154 - - $1,800
-
lb
- -
08 4.111: Add equipment/ operators to reduce production bottleneck $29,052 $6,600 - - - $29,052 -
09 4.513: Re-arrange equipment layout to reduce labor costs $109,188 $7,050 - - - - $109,188
TOTAL RECOMMENDED $175,254 $20,059 $30,736
434,152
kWh
$4,478
-
kW-mo/yr
$1,800
-
lb
$29,052 $109,188
TOTAL IMPLEMENTED $164,605 $14,024 $20,683
292,480
kWh
$3,882
-
kW-mo/yr
$1,800
-
lb
$29,052 $109,188
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Solid Waste (non-haz) Savings Personnel Changes Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs