ITAC Assessment: AS0312
ITAC logo
ITAC Assessment: AS0312
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Plating and grinding of chrome-coated pieces
NAICS
n/a
SIC 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring
Sales Range $500
k
to 1
M
# of Employees 11
Plant Area 4,080
ft2
Annual Production 1,600
units
Production Hrs. Annual 2,428
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $40,482 530,000
kWh
Electricity Demand $1,690 1,063
kW-mo/yr
Electricity Fees $2,987 -
Natural Gas $29,867 4,224
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $20,847 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $19,723

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.7221: Lower temperature during the winter season and vice-versa $95 $20 $70
971
kWh
$25
-
kW-mo/yr
-
02 2.4133: Use most efficient type of electric motors $16 $22 $12
164
kWh
$4
-
kW-mo/yr
-
03 2.7142: Utilize higher efficiency lamps and/or ballasts $110 $265 $82
1,124
kWh
$28
-
kW-mo/yr
-
04 2.7145: Install skylights $458 $747 $458
6,278
kWh
- -
05 2.4231: Reduce the pressure of compressed air to the minimum required $666 $60 $607
8,322
kWh
$59
-
kW-mo/yr
-
06 3.6192: Use a less expensive method of waste removal $779 $60 - - $779
07 3.5316: Contract a wood pallet recycling company $576 $60 - - $576
08 4.426: Modify workload $2,000 $2,640 - - $2,000
09 4.122: Develop standard procedures to improve internal yields $16,147 $1,786 - - $16,147
TOTAL RECOMMENDED $20,847 $5,660 $1,229
16,859
kWh
$116
-
kW-mo/yr
$19,502
TOTAL IMPLEMENTED $19,723 $4,853 $164
2,259
kWh
$57
-
kW-mo/yr
$19,502
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs