ITAC Assessment: AS0302
ITAC logo
ITAC Assessment: AS0302
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2001
Principal Product Aluminum soft drink cans
NAICS
n/a
SIC 3411: Metal Cans
Sales Range $50
M
to 100
M
# of Employees 98
Plant Area 100,000
ft2
Annual Production 1,300,000,000
pieces
Production Hrs. Annual 8,664
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $1,067,820 21,437,700
kWh
Electricity Fees $77,951 -
Natural Gas $606,069 89,270
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $447,814 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Primary Product Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $872 $2,853 n/a $872
16,316
kWh
-
02 2.7145: Install skylights $8,700 $14,940 n/a $8,700
162,490
kWh
-
03 2.4133: Use most efficient type of electric motors $753 $398 n/a $753
14,059
kWh
-
04 2.7221: Lower temperature during the winter season and vice-versa $1,308 $30 n/a $1,308
24,424
kWh
-
05 2.7135: Install occupancy sensors $147 $450 n/a $147
2,739
kWh
-
06 2.4231: Reduce the pressure of compressed air to the minimum required $47,510 $360 n/a $47,510
887,366
kWh
-
07 2.7232: Replace existing hvac unit with high efficiency model $1,740 $4,200 n/a $1,740
32,495
kWh
-
08 4.611: Begin a practice of predictive / preventative maintenance $386,784 $145,968 n/a - $386,784
TOTAL RECOMMENDED $447,814 $169,199 $61,030
1,139,889
kWh
$386,784
TOTAL IMPLEMENTED - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Primary Product Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs