| Assessment Year | 2001 |
|---|---|
| Principal Product | Aluminum soft drink cans |
| NAICS |
n/a
|
| SIC | 3411: Metal Cans |
| Sales Range | $50 M to 100M |
| # of Employees | 98 |
| Plant Area |
100,000
ft2
|
| Annual Production | 1,300,000,000
pieces
|
| Production Hrs. Annual | 8,664
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $1,067,820 | 21,437,700 |
kWh
|
$0.050 |
| Electricity Fees | $77,951 | - |
|
- |
| Natural Gas | $606,069 | 89,270 |
MMBtu
|
$6.79 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $447,814 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | - | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Primary Product Savings |
|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $872 | $2,853 | n/a |
$872
16,316
kWh
|
- |
| 02 | 2.7145: Install skylights | $8,700 | $14,940 | n/a |
$8,700
162,490
kWh
|
- |
| 03 | 2.4133: Use most efficient type of electric motors | $753 | $398 | n/a |
$753
14,059
kWh
|
- |
| 04 | 2.7221: Lower temperature during the winter season and vice-versa | $1,308 | $30 | n/a |
$1,308
24,424
kWh
|
- |
| 05 | 2.7135: Install occupancy sensors | $147 | $450 | n/a |
$147
2,739
kWh
|
- |
| 06 | 2.4231: Reduce the pressure of compressed air to the minimum required | $47,510 | $360 | n/a |
$47,510
887,366
kWh
|
- |
| 07 | 2.7232: Replace existing hvac unit with high efficiency model | $1,740 | $4,200 | n/a |
$1,740
32,495
kWh
|
- |
| 08 | 4.611: Begin a practice of predictive / preventative maintenance | $386,784 | $145,968 | n/a | - | $386,784 |
| TOTAL RECOMMENDED | $447,814 | $169,199 |
$61,030
1,139,889
kWh
|
$386,784 | ||
| TOTAL IMPLEMENTED | - | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Primary Product Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs