| Assessment Year | 2001 |
|---|---|
| Principal Product | Industrial and automotive spray booths |
| NAICS |
n/a
|
| SIC | 3444: Sheet Metal Work |
| Sales Range | $5 M to 10M |
| # of Employees | 34 |
| Plant Area |
12,000
ft2
|
| Annual Production | 300
pieces
|
| Production Hrs. Annual | 2,168
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $31,633 | 346,475 |
kWh
|
$0.091 |
| Electricity Demand | $2,990 | 1,881 |
kW-mo/yr
|
$1.59 |
| Electricity Fees | $2,643 | - |
|
- |
| Natural Gas | $31,766 | 5,079 |
MMBtu
|
$6.25 |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $57,356 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $4,032 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Personnel Changes Savings | Administrative Changes Savings |
|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,381 | $2,549 |
$1,138
15,314
kWh
|
$243
-
kW-mo/yr
|
- | - | - | |
| 02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,767 | $5,107 |
$1,980
22,354
kWh
|
$787
-
kW-mo/yr
|
- | - | - | |
| 03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $388 | $388 |
$279
3,759
kWh
|
$109
-
kW-mo/yr
|
- | - | - | |
| 04 | 3.6192: Use a less expensive method of waste removal | $4,032 | $110 | - | - | - | - | $4,032 | |
| 05 | 4.454: Modify startup/shutdown times | $48,788 | $383 | - | - |
$28,559
-
MMBtu
|
$20,229 | - | |
| TOTAL RECOMMENDED | $57,356 | $8,537 |
$3,397
41,427
kWh
|
$1,139
-
kW-mo/yr
|
$28,559
-
MMBtu
|
$20,229 | $4,032 | ||
| TOTAL IMPLEMENTED | $4,032 | $110 | - | - | - | - | $4,032 | ||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs