ITAC Assessment: AS0289
ITAC logo
ITAC Assessment: AS0289
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 2000
Principal Product Cutting and Machine Tool Accessories
NAICS
n/a
SIC 3545: Cutting Tools, Machine Tool Accessories, and Machinists' Precision Measuring Devices
Sales Range $10
M
to 50
M
# of Employees 95
Plant Area 35,000
ft2
Annual Production 6,000
pieces
Production Hrs. Annual 2,625
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $105,139 1,111,372
kWh
Electricity Demand $7,947 4,654
kW-mo/yr
Electricity Fees $6,754 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $38,322 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $37,634

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $1,898 $18,153 $1,058
22,274
kWh
$840
-
kW-mo/yr
- - - -
02 2.7232: Replace existing hvac unit with high efficiency model $4,081 $9,000 $2,691
56,858
kWh
$1,390
-
kW-mo/yr
- - - -
03 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $1,126 $140 $632
13,189
kWh
$494
-
kW-mo/yr
- - - -
04 2.4314: Use synthetic lubricant $1,048 $694 $95
2,052
kWh
$117
-
kW-mo/yr
$493
-
gal
- $343 -
05 2.7142: Utilize higher efficiency lamps and/or ballasts $481 $221 $179
3,810
kWh
$109
-
kW-mo/yr
- - $193 -
06 3.6192: Use a less expensive method of waste removal $301 $380 - - - $301 - -
07 3.6192: Use a less expensive method of waste removal $387 $60 - - - $387 - -
08 4.521: Clear and rent existing space $29,000 $650 - - - - - $29,000
TOTAL RECOMMENDED $38,322 $29,298 $4,655
98,183
kWh
$2,950
-
kW-mo/yr
$493
-
gal
$688 $536 $29,000
TOTAL IMPLEMENTED $37,634 $28,858 $4,655
98,183
kWh
$2,950
-
kW-mo/yr
$493
-
gal
- $536 $29,000
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Administrative Changes Savings Ancillary Material Cost Savings One-time Revenue or Avoided Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs