Assessment Year | 2000 |
---|---|
Principal Product | Plastic Products |
NAICS |
n/a
|
SIC | 3089: Plastics Products, Not Elsewhere Classified |
Sales Range | $5 M to 10M |
# of Employees | 50 |
Plant Area |
40,000
ft2
|
Annual Production | 6,000,000
lb
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $165,930 | 3,558,910 |
kWh
|
$0.047 |
Electricity Demand | $30,082 | 6,768 |
kW-mo/yr
|
$4.44 |
Electricity Fees | $14,156 | - |
|
- |
Natural Gas | $1,569 | 150 |
MMBtu
|
$10.46 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $92,450 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | By-product Production Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $9,580 | $220 |
$8,421
163,247
kWh
|
$1,159
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.4133: Use most efficient type of electric motors | $4,074 | $7,709 |
$3,582
69,461
kWh
|
$492
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,336 | $5,790 |
$2,900
55,979
kWh
|
$436
-
kW-mo/yr
|
- | - | - | - | |
04 | 3.5217: Reuse / recycle/ sell paper products | $864 | $60 | - | - | - | - | $(-216.0) | $1,080 | |
05 | 4.212: Adopt in-house material generation | $71,251 | $9,660 |
$(-7,949.0)
(-230,363)
kWh
|
- |
$103,200
-
lb
|
$(-24,000.0) | - | - | |
06 | 4.454: Modify startup/shutdown times | $1,239 | $120 | - | - | - | - | $1,239 | - | |
07 | 4.812: Apply for investment incentives | $2,106 | $60 | - | - | - | - | $2,106 | - | |
TOTAL RECOMMENDED | $92,450 | $23,619 |
$6,954
58,324
kWh
|
$2,087
-
kW-mo/yr
|
$103,200
-
lb
|
$(-24,000.0) | $3,129 | $1,080 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | By-product Production Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs