Assessment Year | 1999 |
---|---|
Principal Product | Pre-cast Concrete |
NAICS |
n/a
|
SIC | 3272: Concrete Products, Except Block and Brick |
Sales Range | $10 M to 50M |
# of Employees | 80 |
Plant Area |
56,000
ft2
|
Annual Production | 30,000
ton
|
Production Hrs. Annual | 3,850
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $51,470 | 582,063 |
kWh
|
$0.088 |
Electricity Demand | $4,815 | 2,809 |
kW-mo/yr
|
$1.71 |
Electricity Fees | $4,945 | - |
|
- |
Natural Gas | $12,693 | 1,778 |
MMBtu
|
$7.14 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $209,923 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $11,917 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $1,565 | $3,139 |
$1,210
15,533
kWh
|
$355
-
kW-mo/yr
|
- | - | - | - | - | - | |
02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $4,369 | $1,700 |
$4,369
56,272
kWh
|
- | - | - | - | - | - | - | |
03 | 2.4314: Use synthetic lubricant | $1,269 | $2,378 |
$240
3,224
kWh
|
$53
-
kW-mo/yr
|
$110
-
gal
|
- | - | $866 | - | - | |
04 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $7,548 | $100 |
$6,185
79,426
kWh
|
$1,363
-
kW-mo/yr
|
- | - | - | - | - | - | |
05 | 3.6192: Use a less expensive method of waste removal | $3,402 | $120 | - | - | - | - | $3,402 | - | - | - | |
06 | 3.4155: Meter waste water | $2,057 | $5,000 | - | - | - | - | - | - |
$2,057
-
Tgal
|
- | |
07 | 4.111: Add equipment/ operators to reduce production bottleneck | $178,632 | $50,000 | - | - | - | $(-21,368.0) | - | - | - | $200,000 | |
08 | 4.111: Add equipment/ operators to reduce production bottleneck | $11,081 | $25,000 |
$(-4,606.0)
(-59,203)
kWh
|
$(-6,513.0)
-
kW-mo/yr
|
- | $22,200 | - | - | - | - | |
TOTAL RECOMMENDED | $209,923 | $87,437 |
$7,398
95,252
kWh
|
$(-4,742.0)
-
kW-mo/yr
|
$110
-
gal
|
$832 | $3,402 | $866 |
$2,057
-
Tgal
|
$200,000 | ||
TOTAL IMPLEMENTED | $11,917 | $1,800 |
$10,554
135,698
kWh
|
$1,363
-
kW-mo/yr
|
- | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs