ITAC Assessment: AS0260
ITAC logo
ITAC Assessment: AS0260
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Architectural Mill Work
NAICS
n/a
SIC 2431: Millwork
Sales Range $10
M
to 50
M
# of Employees 110
Plant Area 73,000
ft2
Annual Production 150
thousand feet
Production Hrs. Annual 4,336
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $52,044 619,578
kWh
Electricity Demand $3,588 2,120
kW-mo/yr
Electricity Fees $3,877 -
Natural Gas $5,845 627
MMBtu
LPG $1,498 73
MMBtu
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $29,240 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,960 $8,259 n/a $2,401
31,360
kWh
$559
-
kW-mo/yr
-
02 2.7133: Use separate switches on perimeter lighting which may be turned off when natural light is available $1,591 $1,300 n/a $1,591
20,809
kWh
- -
03 2.4146: Use adjustable frequency drive or multiple speed motors on existing system $9,200 $7,600 n/a $9,200
120,164
kWh
- -
04 2.4231: Reduce the pressure of compressed air to the minimum required $423 $60 n/a $355
4,689
kWh
$68
-
kW-mo/yr
-
05 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves $6,157 $240 n/a $5,168
67,702
kWh
$989
-
kW-mo/yr
-
06 3.5316: Contract a wood pallet recycling company $4,639 $1,060 n/a - - $4,639
07 3.6192: Use a less expensive method of waste removal $3,300 $30 n/a - - $3,300
08 4.111: Add equipment/ operators to reduce production bottleneck $970 - n/a - $970
-
kW-mo/yr
-
TOTAL RECOMMENDED $29,240 $18,549 $18,715
244,724
kWh
$2,586
-
kW-mo/yr
$7,939
TOTAL IMPLEMENTED - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Administrative Changes Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs