ITAC Assessment: AS0259
ITAC logo
ITAC Assessment: AS0259
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Windows and Doors
NAICS
n/a
SIC 3231: Glass Products, Made of Purchased Glass
Sales Range $10
M
to 50
M
# of Employees 125
Plant Area 42,000
ft2
Annual Production 1,000
thousand feet
Production Hrs. Annual 4,352
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $27,507 425,264
kWh
Electricity Demand $5,043 1,782
kW-mo/yr
Electricity Fees $2,483 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $40,644 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings By-product Production Savings
01 2.7232: Replace existing hvac unit with high efficiency model $2,440 $3,500 $2,136
38,394
kWh
$304
-
kW-mo/yr
- - - - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $623 $1,400 $440
7,913
kWh
$183
-
kW-mo/yr
- - - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $155 $100 $91
1,758
kWh
$38
-
kW-mo/yr
- $26 - - -
04 2.7142: Utilize higher efficiency lamps and/or ballasts $242 $240 $142
2,638
kWh
$15
-
kW-mo/yr
- $45 - $40 -
05 3.5217: Reuse / recycle/ sell paper products $2,717 $120 - - - - $2,197 - $520
06 3.4115: Recover and reuse cooling water $27 $38 - - $27
-
Tgal
- - - -
07 4.114: Add/modify equipment to improve drying process $34,440 $1,220 $384
7,034
kWh
- - $34,056 - - -
TOTAL RECOMMENDED $40,644 $6,618 $3,193
57,737
kWh
$540
-
kW-mo/yr
$27
-
Tgal
$34,127 $2,197 $40 $520
TOTAL IMPLEMENTED - - - - - - - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Administrative Changes Savings Ancillary Material Cost Savings By-product Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs