Assessment Year | 1999 |
---|---|
Principal Product | Airbag Components |
NAICS |
n/a
|
SIC | 3451: Screw Machine Products |
Sales Range | $10 M to 50M |
# of Employees | 115 |
Plant Area |
50,000
ft2
|
Annual Production | 13,500,000
pieces
|
Production Hrs. Annual | 7,120
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $225,106 | 3,512,896 |
kWh
|
$0.064 |
Electricity Demand | $15,088 | 8,600 |
kW-mo/yr
|
$1.75 |
Electricity Fees | $15,631 | - |
|
- |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $74,116 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $45,811 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7145: Install skylights | $7,511 | $13,983 |
$7,511
156,800
kWh
|
- | - | - | |
02 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $498 | $20 |
$386
8,206
kWh
|
$112
-
kW-mo/yr
|
- | - | |
03 | 2.7135: Install occupancy sensors | $587 | $1,275 |
$440
9,086
kWh
|
$147
-
kW-mo/yr
|
- | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $226 | $253 |
$132
2,638
kWh
|
$94
-
kW-mo/yr
|
- | - | |
05 | 2.4133: Use most efficient type of electric motors | $2,734 | $4,593 |
$2,232
36,049
kWh
|
$502
-
kW-mo/yr
|
- | - | |
06 | 3.3131: Use evaporation to concentrate material | $18,060 | $5,209 | - | - |
$18,060
-
gal
|
- | |
07 | 3.6192: Use a less expensive method of waste removal | $19,300 | $120 | - | - |
$19,300
-
gal
|
- | |
08 | 4.451: Add additional production shift | $25,200 | $24,000 | - | - | - | $25,200 | |
TOTAL RECOMMENDED | $74,116 | $49,453 |
$10,701
212,779
kWh
|
$855
-
kW-mo/yr
|
$37,360
-
gal
|
$25,200 | ||
TOTAL IMPLEMENTED | $45,811 | $25,668 |
$958
19,930
kWh
|
$353
-
kW-mo/yr
|
$19,300
-
gal
|
$25,200 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Other Liquid (non-haz) Savings | Personnel Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs