ITAC Assessment: AS0245
ITAC logo
ITAC Assessment: AS0245
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Custom Plastic Injection Molding
NAICS
n/a
SIC 3089: Plastics Products, Not Elsewhere Classified
Sales Range $100
M
to 500
M
# of Employees 1,200
Plant Area 250,000
ft2
Annual Production 3,250,000
pieces
Production Hrs. Annual 8,712
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $688,965 20,601,993
kWh
Electricity Demand $341,274 32,474
kW-mo/yr
Electricity Fees $140,076 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $19,532 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* -

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Water Disposal Savings Personnel Changes Savings Ancillary Material Cost Savings
01 2.4133: Use most efficient type of electric motors $5,105 $9,802 $3,149
106,389
kWh
$1,956
-
kW-mo/yr
- - -
02 2.7142: Utilize higher efficiency lamps and/or ballasts $1,495 $1,856 $584
19,637
kWh
$283
-
kW-mo/yr
- $305 $323
03 3.4151: Minimize water usage $12,932 $180 - - $12,932
-
Tgal
- -
TOTAL RECOMMENDED $19,532 $11,838 $3,733
126,026
kWh
$2,239
-
kW-mo/yr
$12,932
-
Tgal
$305 $323
TOTAL IMPLEMENTED - - - - - - -
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs