ITAC Assessment: AS0243
ITAC logo
ITAC Assessment: AS0243
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1999
Principal Product Stretch-Blow Injection Molding
NAICS
n/a
SIC 3085: Plastics Bottles
Sales Range $10
M
to 50
M
# of Employees 50
Plant Area 100,000
ft2
Annual Production 50,000,000
pieces
Production Hrs. Annual 8,568
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $344,698 8,271,102
kWh
Electricity Demand $139,621 15,060
kW-mo/yr
Electricity Fees $527,357 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $178,515 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $7,800

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings Water Consumption Savings By-product Production Savings Increase in Production Savings
01 2.7142: Utilize higher efficiency lamps and/or ballasts $2,432 $3,754 $1,486
35,463
kWh
$946
-
kW-mo/yr
- - - - -
02 2.7121: Utilize daylight whenever possible in lieu of artificial light $3,379 $225 $3,020
68,288
kWh
$359
-
kW-mo/yr
- - - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $6,369 $5,320 $5,149
116,354
kWh
$1,220
-
kW-mo/yr
- - - - -
04 2.7243: Improve air circulation with destratification fans / other methods $3,180 $5,434 $3,180
80,305
kWh
- - - - - -
05 3.6192: Use a less expensive method of waste removal $7,800 $80 - - - $7,800 - - -
06 4.521: Clear and rent existing space $13,172 $5,400 - - $3,672 - - $9,500 -
07 4.111: Add equipment/ operators to reduce production bottleneck $142,183 $196,000 - - - - $(-7,817.0)
-
Tgal
- $150,000
TOTAL RECOMMENDED $178,515 $216,213 $12,835
300,410
kWh
$2,525
-
kW-mo/yr
$3,672 $7,800 $(-7,817.0)
-
Tgal
$9,500 $150,000
TOTAL IMPLEMENTED $7,800 $80 - - - $7,800 - - -
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Personnel Changes Savings Administrative Changes Savings Water Consumption Savings By-product Production Savings Increase in Production Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs