| Assessment Year | 1999 |
|---|---|
| Principal Product | Stretch-Blow Injection Molding |
| NAICS |
n/a
|
| SIC | 3085: Plastics Bottles |
| Sales Range | $10 M to 50M |
| # of Employees | 50 |
| Plant Area |
100,000
ft2
|
| Annual Production | 50,000,000
pieces
|
| Production Hrs. Annual | 8,568
hrs
|
| Location (State) | Arizona |
Facility Energy Cost and Usage
| Source | Yearly Cost | Usage | Unit Cost | |
|---|---|---|---|---|
| Electricity Usage | $344,698 | 8,271,102 |
kWh
|
$0.042 |
| Electricity Demand | $139,621 | 15,060 |
kW-mo/yr
|
$9.27 |
| Electricity Fees | $527,357 | - |
|
- |
| TOTAL YEARLY COSTS | - | |||
| RECOMMENDED SAVINGS* | $178,515 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
| IMPLEMENTED SAVINGS* | $7,800 | |||
Recommendations
| # | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings | By-product Production Savings | Increase in Production Savings |
|---|---|---|---|---|---|---|---|---|---|---|---|
| 01 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $2,432 | $3,754 |
$1,486
35,463
kWh
|
$946
-
kW-mo/yr
|
- | - | - | - | - | |
| 02 | 2.7121: Utilize daylight whenever possible in lieu of artificial light | $3,379 | $225 |
$3,020
68,288
kWh
|
$359
-
kW-mo/yr
|
- | - | - | - | - | |
| 03 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $6,369 | $5,320 |
$5,149
116,354
kWh
|
$1,220
-
kW-mo/yr
|
- | - | - | - | - | |
| 04 | 2.7243: Improve air circulation with destratification fans / other methods | $3,180 | $5,434 |
$3,180
80,305
kWh
|
- | - | - | - | - | - | |
| 05 | 3.6192: Use a less expensive method of waste removal | $7,800 | $80 | - | - | - | $7,800 | - | - | - | |
| 06 | 4.521: Clear and rent existing space | $13,172 | $5,400 | - | - | $3,672 | - | - | $9,500 | - | |
| 07 | 4.111: Add equipment/ operators to reduce production bottleneck | $142,183 | $196,000 | - | - | - | - |
$(-7,817.0)
-
Tgal
|
- | $150,000 | |
| TOTAL RECOMMENDED | $178,515 | $216,213 |
$12,835
300,410
kWh
|
$2,525
-
kW-mo/yr
|
$3,672 | $7,800 |
$(-7,817.0)
-
Tgal
|
$9,500 | $150,000 | ||
| TOTAL IMPLEMENTED | $7,800 | $80 | - | - | - | $7,800 | - | - | - | ||
| Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Personnel Changes Savings | Administrative Changes Savings | Water Consumption Savings | By-product Production Savings | Increase in Production Savings | |||
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs