Assessment Year | 1998 |
---|---|
Principal Product | Drywall |
NAICS |
n/a
|
SIC | 3275: Gypsum Products |
Sales Range | $10 M to 50M |
# of Employees | 55 |
Plant Area |
150,000
ft2
|
Annual Production | 150,000,000
thousand feet
|
Production Hrs. Annual | 8,568
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $381,137 | 8,864,889 |
kWh
|
$0.043 |
Electricity Demand | $145,459 | 15,630 |
kW-mo/yr
|
$9.31 |
Electricity Fees | $34,707 | - |
|
- |
Natural Gas | $1,692,958 | 432,710 |
MMBtu
|
$3.91 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $266,966 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.4314: Use synthetic lubricant | $1,810 | $1,710 |
$184
4,103
kWh
|
$57
-
kW-mo/yr
|
- | - |
$177
-
gal
|
- | - | - | - | $1,392 | |
02 | 2.7232: Replace existing hvac unit with high efficiency model | $2,088 | $3,600 |
$1,546
39,566
kWh
|
$542
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | |
03 | 2.4133: Use most efficient type of electric motors | $11,473 | $23,248 |
$9,087
201,934
kWh
|
$2,386
-
kW-mo/yr
|
- | - | - | - | - | - | - | - | |
04 | 2.2515: Use optimum thickness insulation | $11,065 | $3,346 | - | - |
$11,065
-
MMBtu
|
- | - | - | - | - | - | - | |
05 | 2.2414: Use waste heat from hot flue gases to preheat | $141,705 | $103,000 | - | - |
$141,705
-
MMBtu
|
- | - | - | - | - | - | - | |
06 | 3.5248: Separate and recycle scrap metal to foundry or for sale | $7,760 | $120 | - | - | - | - | - |
$7,760
-
lb
|
- | - | - | - | |
07 | 3.4151: Minimize water usage | $18,668 | $82,192 | - | - |
$17,786
-
MMBtu
|
$882
-
Tgal
|
- | - | - | - | - | - | |
08 | 4.212: Adopt in-house material generation | $72,397 | $325,070 | - | - | - | - | - |
$41,238
-
lb
|
$(-5,880.0) | $(-12,392.0) | $49,431 | - | |
TOTAL RECOMMENDED | $266,966 | $542,286 |
$10,817
245,603
kWh
|
$2,985
-
kW-mo/yr
|
$170,556
-
MMBtu
|
$882
-
Tgal
|
$177
-
gal
|
$48,998
-
lb
|
$(-5,880.0) | $(-12,392.0) | $49,431 | $1,392 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Water Disposal Savings | Other Liquid (non-haz) Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Primary Raw Material Savings | Ancillary Material Cost Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs