ITAC Assessment: AS0217
ITAC logo
ITAC Assessment: AS0217
Grant Funding Opportunity NOW OPEN
Up to $300k at 50% cost share for qualifying* projects.
Grant Funding Opportunity Open
Qualifying* small and medium-sized US manufacturers, that received an ITAC, Onsite Energy/CHP TAP, or qualified equivalent assessment since 2018 can now apply for grants for implementation of assessment recommendations at up to 50% of qualifying* project costs with a maximum of $300,000 per grant.
IMPORTANT: The grant program now operates on a rolling basis and applications may be submitted at any time through the year, with quarterly reviews.
*See Full Grant Solicitation for full qualification and selection details.
Assessment Year 1998
Principal Product Commercial Printing
NAICS
n/a
SIC 2752: Commercial Printing, Lithographic
Sales Range $5
M
to 10
M
# of Employees 60
Plant Area 30,000
ft2
Annual Production 5,000,000
lb
Production Hrs. Annual 5,730
hrs
Location (State) Arizona

Facility Energy Cost and Usage

Source Yearly Cost Usage
Electricity Usage $82,051 1,276,964
kWh
Electricity Demand $36,340 4,717
kW-mo/yr
Electricity Fees $10,968 -
TOTAL YEARLY COSTS -
RECOMMENDED SAVINGS* $221,665 *Non-energy impacts included in savings.
IMPLEMENTED SAVINGS* $17,243

Recommendations

# Description Yearly Savings* Imp'd Cost* Status Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
01 2.7314: Reduce ventilation air $1,882 $1,100 $1,882
26,964
kWh
- - - - - -
02 2.7135: Install occupancy sensors $465 $1,200 $350
4,982
kWh
$115
-
kW-mo/yr
- - - - -
03 2.7142: Utilize higher efficiency lamps and/or ballasts $6,438 $10,732 $5,366
76,495
kWh
$1,072
-
kW-mo/yr
- - - - -
04 2.7232: Replace existing hvac unit with high efficiency model $6,108 $4,800 $5,341
76,202
kWh
$767
-
kW-mo/yr
- - - - -
05 2.4133: Use most efficient type of electric motors $916 $1,089 $751
10,844
kWh
$165
-
kW-mo/yr
- - - - -
06 2.7122: Disconnect ballasts $354 $15 $321
4,689
kWh
$33
-
kW-mo/yr
- - - - -
07 2.7313: Recycle air for heating, ventilation and air conditioning $358 $15 $358
4,982
kWh
- - - - - -
08 2.7224: Reduce space conditioning during non-working hours $469 $225 $469
6,741
kWh
- - - - - -
09 2.4314: Use synthetic lubricant $255 $292 $141
2,052
kWh
$31
-
kW-mo/yr
$11
-
gal
- - - $72
10 3.6192: Use a less expensive method of waste removal $15,720 $60 - - - - $3,220 - $12,500
11 3.6192: Use a less expensive method of waste removal $700 $60 - - - - $700 - -
12 4.113: Install refrigeration system to cool product $188,000 $450,000 - - - $108,000 - $80,000 -
TOTAL RECOMMENDED $221,665 $469,588 $14,979
213,951
kWh
$2,183
-
kW-mo/yr
$11
-
gal
$108,000 $3,920 $80,000 $12,572
TOTAL IMPLEMENTED $17,243 $360 $790
11,430
kWh
$33
-
kW-mo/yr
- - $3,920 - $12,500
Yearly Savings* Imp'd Cost* Electricity Usage Savings Electricity Demand Savings Other Liquid (non-haz) Savings Personnel Changes Savings Administrative Changes Savings Primary Raw Material Savings Ancillary Material Cost Savings
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs