Assessment Year | 1997 |
---|---|
Principal Product | Semiconductors |
NAICS |
n/a
|
SIC | 3674: Semiconductors and Related Devices |
Sales Range | $10 M to 50M |
# of Employees | 200 |
Plant Area |
30,000
ft2
|
Annual Production | 110,000
pieces
|
Production Hrs. Annual | 3,150
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $265,904 | 4,150,645 |
kWh
|
$0.064 |
Electricity Demand | $53,515 | 7,269 |
kW-mo/yr
|
$7.36 |
Electricity Fees | $29,571 | - |
|
- |
Natural Gas | $87,870 | 18,647 |
MMBtu
|
$4.71 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $1,382,887 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | - |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7135: Install occupancy sensors | $286 | $450 |
$240
3,517
kWh
|
$46
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
02 | 2.7111: Reduce illumination to minimum necessary levels | $287 | $300 |
$199
2,931
kWh
|
$88
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.7122: Disconnect ballasts | $277 | $15 |
$247
3,517
kWh
|
$30
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $122 | $348 |
$109
1,465
kWh
|
$13
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $7,357 | $3,800 |
$7,357
104,924
kWh
|
- | - | - | - | - | - | - | - | |
06 | 2.4133: Use most efficient type of electric motors | $3,642 | $1,827 |
$3,168
45,135
kWh
|
$474
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
07 | 3.3131: Use evaporation to concentrate material | $1,813 | $5,185 |
$(-149.0)
(-2,052)
kWh
|
- | - |
$2,142
-
gal
|
$(-180.0) | - | - | - | - | |
08 | 3.6192: Use a less expensive method of waste removal | $1,674 | $60 | - | - | - | - | - | $1,674 | - | - | - | |
09 | 4.212: Adopt in-house material generation | $1,487 | $1,020 | - | - | - | - | $375 | $1,232 | $(-111.0) |
$(-9.0)
-
Tgal
|
- | |
10 | 4.631: Install an uninteruptable power supply | $1,365,942 | $500,000 |
$79,941
1,140,387
kWh
|
$17,664
-
kW-mo/yr
|
$(-31,663.0)
-
MMBtu
|
- | - | - | - | - | $1,300,000 | |
TOTAL RECOMMENDED | $1,382,887 | $513,005 |
$91,112
1,299,824
kWh
|
$18,315
-
kW-mo/yr
|
$(-31,663.0)
-
MMBtu
|
$2,142
-
gal
|
$195 | $2,906 | $(-111.0) |
$(-9.0)
-
Tgal
|
$1,300,000 | ||
TOTAL IMPLEMENTED | - | - | - | - | - | - | - | - | - | - | - | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings | Primary Product Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs