Assessment Year | 1997 |
---|---|
Principal Product | Investment Castings |
NAICS |
n/a
|
SIC | 3324: Steel Investment Foundries |
Sales Range | $10 M to 50M |
# of Employees | 430 |
Plant Area |
185,589
ft2
|
Annual Production | 5,500,000
pieces
|
Production Hrs. Annual | 5,100
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $611,070 | 12,605,510 |
kWh
|
$0.048 |
Electricity Demand | $149,274 | 40,840 |
kW-mo/yr
|
$3.66 |
Electricity Fees | $130,201 | - |
|
- |
Natural Gas | $97,811 | 62,276 |
MMBtu
|
$1.57 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $140,310 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $120,307 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $13,162 | $2,895 |
$7,814
199,883
kWh
|
$5,348
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $4,087 | $8,920 |
$2,551
65,358
kWh
|
$1,536
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
03 | 2.7135: Install occupancy sensors | $796 | $1,575 |
$519
13,482
kWh
|
$277
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
04 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $3,864 | $8,680 |
$2,304
58,910
kWh
|
$1,560
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
05 | 2.4146: Use adjustable frequency drive or multiple speed motors on existing system | $15,343 | $40,705 |
$15,343
392,438
kWh
|
- | - | - | - | - | - | - | - | |
06 | 2.4133: Use most efficient type of electric motors | $15,546 | $16,449 |
$9,276
237,397
kWh
|
$6,270
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
07 | 2.7232: Replace existing hvac unit with high efficiency model | $21,613 | $12,000 |
$15,503
396,542
kWh
|
$6,110
-
kW-mo/yr
|
- | - | - | - | - | - | - | |
08 | 3.3131: Use evaporation to concentrate material | $1,522 | $500 | - | - |
$(-7.0)
-
MMBtu
|
$1,709
-
gal
|
- | $(-180.0) | - | - | - | |
09 | 3.3131: Use evaporation to concentrate material | $47,154 | $38,923 | - | - |
$(-418.0)
-
MMBtu
|
- |
$70,522
-
gal
|
$(-22,950.0) | - | - | - | |
10 | 4.212: Adopt in-house material generation | $6,013 | $1,500 |
$(-36.0)
879
kWh
|
- | - | - | - | - | - | $6,095 |
$(-46.0)
-
Tgal
|
|
11 | 4.811: Demolish old building to reduce tax and insurance bills | $11,210 | $100 | - | - | - | - | - | - | $11,210 | - | - | |
TOTAL RECOMMENDED | $140,310 | $132,247 |
$53,274
1,364,889
kWh
|
$21,101
-
kW-mo/yr
|
$(-425.0)
-
MMBtu
|
$1,709
-
gal
|
$70,522
-
gal
|
$(-23,130.0) | $11,210 | $6,095 |
$(-46.0)
-
Tgal
|
||
TOTAL IMPLEMENTED | $120,307 | $81,287 |
$35,108
900,059
kWh
|
$19,264
-
kW-mo/yr
|
$(-425.0)
-
MMBtu
|
$1,709
-
gal
|
$70,522
-
gal
|
$(-23,130.0) | $11,210 | $6,095 |
$(-46.0)
-
Tgal
|
||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Natural Gas Savings | Other Liquid (non-haz) Savings | Other Liquid (haz) Savings | Personnel Changes Savings | Administrative Changes Savings | Ancillary Material Cost Savings | Water Consumption Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs