Assessment Year | 1997 |
---|---|
Principal Product | Anodizing |
NAICS |
n/a
|
SIC | 3471: Electroplating, Plating, Polishing, Anodizing, and Coloring |
Sales Range | $5 M to 10M |
# of Employees | 150 |
Plant Area |
60,000
ft2
|
Annual Production | 1,036,000
pieces
|
Production Hrs. Annual | 8,760
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $332,834 | 4,523,447 |
kWh
|
$0.074 |
Electricity Demand | $19,600 | 11,135 |
kW-mo/yr
|
$1.76 |
Electricity Fees | $24,146 | - |
|
- |
Natural Gas | $9,574 | 1,715 |
MMBtu
|
$5.58 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $53,613 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $17,017 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|---|---|
01 | 2.7228: Avoid introducing hot, humid, or dirty air into hvac system | $11,182 | $2,080 |
$7,607
154,748
kWh
|
$3,575
-
kW-mo/yr
|
- | - | - | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $5,290 | $7,006 |
$4,375
88,804
kWh
|
$915
-
kW-mo/yr
|
- | - | - | - | |
03 | 2.4231: Reduce the pressure of compressed air to the minimum required | $815 | $70 |
$623
12,603
kWh
|
$192
-
kW-mo/yr
|
- | - | - | - | |
04 | 2.4133: Use most efficient type of electric motors | $2,230 | $1,092 |
$1,806
36,635
kWh
|
$424
-
kW-mo/yr
|
- | - | - | - | |
05 | 2.7232: Replace existing hvac unit with high efficiency model | $8,943 | $7,500 |
$7,218
146,835
kWh
|
$1,725
-
kW-mo/yr
|
- | - | - | - | |
06 | 2.4236: Eliminate leaks in inert gas and compressed air lines/ valves | $714 | $40 |
$578
11,723
kWh
|
$136
-
kW-mo/yr
|
- | - | - | - | |
07 | 2.7111: Reduce illumination to minimum necessary levels | $1,901 | $70 |
$1,279
26,084
kWh
|
$622
-
kW-mo/yr
|
- | - | - | - | |
08 | 2.7135: Install occupancy sensors | $1,348 | $1,425 |
$1,208
24,619
kWh
|
$140
-
kW-mo/yr
|
- | - | - | - | |
09 | 3.4113: Treat and reuse rinse waters | $4,004 | $950 | - | - |
$4,004
-
Tgal
|
- | - | - | |
10 | 3.1191: Change procedures / equipment / operating conditions | $15,110 | $4,500 | - | - | - |
$5,360
-
lb
|
$9,750 | - | |
11 | 3.6192: Use a less expensive method of waste removal | $2,076 | $30 | - | - | - | - | - | $2,076 | |
TOTAL RECOMMENDED | $53,613 | $24,763 |
$24,694
502,051
kWh
|
$7,729
-
kW-mo/yr
|
$4,004
-
Tgal
|
$5,360
-
lb
|
$9,750 | $2,076 | ||
TOTAL IMPLEMENTED | $17,017 | $3,312 |
$10,614
215,709
kWh
|
$4,327
-
kW-mo/yr
|
- | - | - | $2,076 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Solid Waste (non-haz) Savings | Personnel Changes Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs