Assessment Year | 1997 |
---|---|
Principal Product | Integrated Circuits |
NAICS |
n/a
|
SIC | 3674: Semiconductors and Related Devices |
Sales Range | $1 M to 5M |
# of Employees | 350 |
Plant Area |
101,947
ft2
|
Annual Production | 25,000
pieces
|
Production Hrs. Annual | 8,400
hrs
|
Location (State) | Arizona |
Facility Energy Cost and Usage
Source | Yearly Cost | Usage | Unit Cost | |
---|---|---|---|---|
Electricity Usage | $325,064 | 6,452,228 |
kWh
|
$0.050 |
Electricity Demand | $29,708 | 10,860 |
kW-mo/yr
|
$2.74 |
Electricity Fees | $25,645 | - |
|
- |
Natural Gas | $16,543 | 3,239 |
MMBtu
|
$5.11 |
TOTAL YEARLY COSTS | - | |||
RECOMMENDED SAVINGS* | $118,932 |
See individual recommendations below
*Non-energy impacts included in savings.
|
||
IMPLEMENTED SAVINGS* | $112,016 |
Recommendations
# | Description | Yearly Savings* | Imp'd Cost* | Status | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Administrative Changes Savings |
---|---|---|---|---|---|---|---|---|
01 | 2.7111: Reduce illumination to minimum necessary levels | $312 | - |
$134
3,517
kWh
|
$178
-
kW-mo/yr
|
- | - | |
02 | 2.7142: Utilize higher efficiency lamps and/or ballasts | $861 | $570 |
$619
16,120
kWh
|
$242
-
kW-mo/yr
|
- | - | |
03 | 2.1121: Use insulation in furnaces to facilitate heating / cooling | $393 | $300 |
$280
7,327
kWh
|
$113
-
kW-mo/yr
|
- | - | |
04 | 2.4133: Use most efficient type of electric motors | $3,343 | $3,980 |
$2,602
67,409
kWh
|
$741
-
kW-mo/yr
|
- | - | |
05 | 2.6218: Turn off equipment when not in use | $188 | - |
$135
3,517
kWh
|
$53
-
kW-mo/yr
|
- | - | |
06 | 3.1191: Change procedures / equipment / operating conditions | $1,880 | $1,880 | - | - |
$1,880
-
Tgal
|
- | |
07 | 3.4151: Minimize water usage | $800 | - | - | - |
$800
-
Tgal
|
- | |
08 | 4.811: Demolish old building to reduce tax and insurance bills | $1,460 | $75 | - | - | - | $1,460 | |
09 | 4.512: Condense operation into one building | $109,695 | $15,000 |
$8,822
228,605
kWh
|
$12,188
-
kW-mo/yr
|
- | $88,685 | |
TOTAL RECOMMENDED | $118,932 | $21,805 |
$12,592
326,495
kWh
|
$13,515
-
kW-mo/yr
|
$2,680
-
Tgal
|
$90,145 | ||
TOTAL IMPLEMENTED | $112,016 | $15,645 |
$9,441
244,725
kWh
|
$12,430
-
kW-mo/yr
|
- | $90,145 | ||
Yearly Savings* | Imp'd Cost* | Electricity Usage Savings | Electricity Demand Savings | Water Disposal Savings | Administrative Changes Savings |
*Savings and costs are best estimates based on the center's site visit, associated engineering analysis, and typical capital and labor costs